Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   The probability distribution of project comp... Start Learning for Free
The probability distribution of project completion in PERT follows following distribution
  • a)
    Normal
  • b)
    Poisson’s
  • c)
    Beta
  • d)
    Exponential
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
The probability distribution of project completion in PERT follows fo...
The PERT (Program Evaluation and Review Technique) method is commonly used in project management to estimate the completion time of a project. It considers three time estimates for each activity: optimistic time (O), most likely time (M), and pessimistic time (P). These estimates are used to calculate the project completion time and the probability distribution of completion time.

The probability distribution of project completion in PERT follows a normal distribution. Here's an explanation of why this is the case:

1. PERT formula:
The PERT formula is used to calculate the expected completion time (TE) of a project. It is given by:
TE = (O + 4M + P) / 6

2. Central Limit Theorem:
The Central Limit Theorem states that the sum (or average) of a large number of independent and identically distributed random variables will be approximately normally distributed, regardless of the shape of the original distribution. In the case of PERT, the completion time of a project is the sum of completion times of individual activities, which are assumed to be independent and identically distributed.

3. Weighted average:
In the PERT formula, the most likely time (M) is given the highest weight (4), while the optimistic time (O) and pessimistic time (P) are given lower weights (1 each). This weighting scheme ensures that the most likely time has a greater influence on the expected completion time.

4. Symmetry of distribution:
The PERT distribution is symmetric around the most likely time (M), which means that the probabilities of completing the project before or after the expected completion time are equal. This symmetry is a characteristic of the normal distribution.

5. Bell-shaped curve:
The normal distribution is characterized by a bell-shaped curve, with the mean, median, and mode all coinciding at the most likely time (M). This shape reflects the fact that most projects are likely to be completed close to the expected completion time.

In conclusion, the probability distribution of project completion in PERT follows a normal distribution because of the application of the Central Limit Theorem, the weighted average of time estimates, the symmetry of the distribution, and the bell-shaped curve.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer?
Question Description
The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The probability distribution of project completion in PERT follows following distributiona) Normalb) Poisson’sc) Betad) ExponentialCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev