Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  In an MRP system, component demand isa)foreca... Start Learning for Free
In an MRP system, component demand is
  • a)
    forecasted
  • b)
    calculated by the MRP system from the master production schedule
  • c)
    established by the master production schedule
  • d)
    ignored
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
In an MRP system, component demand isa)forecastedb)calculated by the M...
Component Demand in an MRP System

In an MRP (Material Requirements Planning) system, component demand refers to the quantity of components or raw materials needed to fulfill the production requirements specified by the master production schedule (MPS). The MRP system calculates this demand by evaluating the production plan and determining the materials needed for each stage of production.

1. Forecasted Demand
- Forecasted demand refers to the estimated quantity of components that will be required in the future based on historical data, market trends, and other relevant factors.
- While forecasting is an important aspect of production planning, it is not the primary method for determining component demand in an MRP system.

2. Calculation by MRP System
- The MRP system derives component demand by analyzing the MPS, which provides information about the production schedule, including the quantities and timing of finished goods required.
- Based on the production plan, the MRP system breaks down the finished goods requirements into the necessary components and raw materials needed to produce them.
- It calculates the quantities of each component required by considering factors such as the bill of materials, lead times, inventory levels, and order quantities.
- The MRP system takes into account the timing of the production schedule, ensuring that components are available when needed and avoiding shortages or excess inventory.

3. Role of the Master Production Schedule
- The master production schedule (MPS) serves as the primary input to the MRP system.
- The MPS outlines the production plan, specifying the quantities of finished goods to be manufactured in each time period.
- It takes into account factors such as customer demand, sales forecasts, production capacity, and inventory levels.
- The MRP system uses the MPS as a basis for calculating the component demand, ensuring that the necessary materials are available to support the production schedule.

4. Ignoring Component Demand
- Ignoring component demand would undermine the effectiveness of an MRP system.
- Without considering the component requirements, it would be impossible to ensure that the necessary materials are available in the right quantities and at the right time.
- This could result in production delays, stockouts, excess inventory, increased costs, and customer dissatisfaction.

Therefore, the correct answer is option 'B' - Component demand is calculated by the MRP system from the master production schedule. The MRP system analyzes the MPS to determine the quantities of components needed for production, considering various factors to ensure efficient material planning and production scheduling.
Free Test
Community Answer
In an MRP system, component demand isa)forecastedb)calculated by the M...
MRP (Material Requirement Planning):
MRP function is a computational technique with the help of which the master schedule for end products is converted into a detailed schedule for raw materials and components used in the end proudct.
Input to MRP:
(i) Master production schedule.
(ii) The bill of material.
(iii) Inventory records relating to raw materials.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer?
Question Description
In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In an MRP system, component demand isa)forecastedb)calculated by the MRP system from the master production schedulec)established by the master production scheduled)ignoredCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev