A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part is
  • a)
    Order 1000 units whenever the inventory level drops to 200 units
  • b)
    Order 900 units whenever the inventory level drops to 150 units
  • c)
    Order 1200 units whenever the inventory level drops to 300 units
  • d)
    Order 800 units whenever the inventory level drops to 100 units
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
A company requires 100 units per day of a particular part. It costs ₹...
D = 100 units/day
Co = ₹ 100 per order
L = 12 days
C1 = ₹ 0.02 per unit per day
Cycle time, t = EOQ/D = 1000/100 = 10 days
Since the lead time, L = 12 days exceeds the cycle time t = 10
days,
Le = L - mt = 12 - 1 x 10 = 2 days
Largest integer, m ≤ L/t
≤ 12/10 = 1
The re-order point therefore occurs when the inventory level drops to Le X D = 2 x 100 = 200 parts.
Hence, the inventory policy for ordering the part is: Order 1000 units whenever the inventory level drops to 200 units
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer?
Question Description
A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A company requires 100 units per day of a particular part. It costs ₹100 to initiate a purchase order. A part kept in storage is estimated to cost about ₹ 0.02 per day. The lead time between placing and receiving an order is 12 days. The optimum inventory policy for ordering the part isa)Order 1000 units whenever the inventory level drops to 200 unitsb)Order 900 units whenever the inventory level drops to 150 unitsc)Order 1200 units whenever the inventory level drops to 300 unitsd)Order 800 units whenever the inventory level drops to 100 unitsCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev