A harvester's team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?
  • a)
    9.0 hectares
  • b)
    8.5 hectares
  • c)
    8.0 hectares
  • d)
    7.5 hectares
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
A harvesters team had to harvest 170 hectares of a field. For the firs...
To find the answer, let's break down the problem step by step:

Step 1: Find the total number of hectares harvested in the first four days.
Let's assume that the team harvested x hectares per day for the first four days. Therefore, the total number of hectares harvested in the first four days would be 4x.

Step 2: Find the total number of hectares harvested in the remaining days.
Since the work was finished eight days before the planned date, the remaining days would be 8 - 4 = 4 days.
According to the problem, the team started harvesting at double the rate planned for every day. So, for the remaining four days, they harvested 2x hectares per day. Therefore, the total number of hectares harvested in the remaining days would be 4 * 2x = 8x.

Step 3: Find the total number of hectares harvested.
The problem states that the team had to harvest 170 hectares in total. Therefore, the equation would be:
4x + 8x = 170
12x = 170
x = 170/12
x = 14.17

Step 4: Find the number of hectares harvested by the team each day as per the initial plan.
Since the question asks for the number of hectares harvested per day as per the initial plan, the answer would be x = 14.17 hectares per day.

Therefore, the correct answer is option (B) 8.5 hectares.
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer?
Question Description
A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A harvesters team had to harvest 170 hectares of a field. For the first four days, the team harvested as per the plan. After that, they started harvesting at double the rate planned for every day. So, the work was finished eight days before the planned date. How many hectares had to be harvested by the team each day as per the initial plan?a)9.0 hectaresb)8.5 hectaresc)8.0 hectaresd)7.5 hectaresCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev