In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainage 
  • a)
    107 m
  • b)
    97 m
  • c)
    100 m
  • d)
    117 m
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
In a road embankment work, the reduced level of formation bed at Zero ...
Given information:
- Reduced level of formation bed at Zero m chainage = 107 m
- Downward gradient of the road = 1 in 100

To determine:
- Reduced level of formation bed at 1000 m chainage

Explanation:

The downward gradient of 1 in 100 means that for every 100 units of horizontal distance, there is a 1 unit decrease in vertical distance.

We can use this information to calculate the change in reduced level over a given distance.

Step 1: Calculate the change in reduced level per unit distance.

Change in reduced level per unit distance = Gradient × Distance = 1/100 × 1000 = 10 m

This means that for every 1000 m of horizontal distance, there is a decrease of 10 m in vertical distance.

Step 2: Calculate the reduced level at 1000 m chainage.

Reduced level at 1000 m chainage = Reduced level at Zero m chainage - Change in reduced level

= 107 m - 10 m

= 97 m

Therefore, the reduced level of the formation bed at 1000 m chainage is 97 m (Option B).
Free Test
Community Answer
In a road embankment work, the reduced level of formation bed at Zero ...
Given data,
The reduced level of formation bed at Zero m chainage = 107 m
A downward gradient = 1 in 100
Hence, the reduced level of formation bed at 1000 m chainage is
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer?
Question Description
In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In a road embankment work, the reduced level of formation bed at Zero m chainage is 107 m. The road is supposed to have a downward gradient of 1 in 100. Determine the reduced level of formation bed at 1000 m chainagea)107 mb)97 mc)100 md)117 mCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev