Computer Science Engineering (CSE) Exam  >  Computer Science Engineering (CSE) Questions  >  Time estimates of an activity in a PERT netwo... Start Learning for Free
Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84?
Most Upvoted Answer
Time estimates of an activity in a PERT network are: Optimistic time t...
Solution:

Given data:
Optimistic time to = 9 days;
Pessimistic time tp = 21 days;
Most likely time te = 15 days.

To find:
The approximate probability of completion of this activity in 13 days.

Formula used:
The formula used in PERT analysis for Expected Time (T) is as follows:
T = (to + 4tm + tp) / 6

Where,
to = Optimistic time
tm = Most likely time
tp = Pessimistic time

The formula used for standard deviation (SD) is as follows:
SD = (tp - to) / 6

The formula used for calculating z-score is as follows:
z = (x - T) / SD

Where,
x = Time taken to complete an activity

The formula used for probability calculation is as follows:
P(x <= t)="">

Where,
Φ(z) is the standard normal cumulative distribution function.

Steps to be followed:

Step 1: Calculate the Expected time (T)

T = (to + 4tm + tp) / 6
= (9 + 4(15) + 21) / 6
= 15 days

Step 2: Calculate the Standard deviation (SD)

SD = (tp - to) / 6
= (21 - 9) / 6
= 2 days

Step 3: Calculate the z-score for x = 13 days

z = (x - T) / SD
= (13 - 15) / 2
= -1

Step 4: Find the probability of completing the activity in 13 days

P(x <= t)="">
= Φ(-1)
= 0.1587

Therefore, the approximate probability of completion of this activity in 13 days is 0.1587 or 15.87%. Therefore, the correct option is A. 0.16.

Conclusion:

The approximate probability of completion of this activity in 13 days is 0.1587 or 15.87%.
Community Answer
Time estimates of an activity in a PERT network are: Optimistic time t...
PERT Network Probability Calculation

Given data:
Optimistic time to = 9 days
Pessimistic time tp = 21 days
Most likely time te = 15 days

Finding Expected Time
The expected time (tE) can be calculated as follows:
tE = (to + 4tm + tp) / 6
where,
to = optimistic time
tp = pessimistic time
tm = most likely time

Substituting the given values in the above formula, we get:
tE = (9 + 4*15 + 21) / 6 = 15 days

Finding Variance
The variance (σ2) can be calculated as follows:
σ2 = [(tp - to) / 6]2
where,
to = optimistic time
tp = pessimistic time

Substituting the given values in the above formula, we get:
σ2 = [(21 - 9) / 6]2 = 2.67 days2

Finding Standard Deviation
The standard deviation (σ) can be calculated as follows:
σ = √σ2

Substituting the value of σ2 we get:
σ = √2.67 = 1.63 days

Calculating Probability of Completion in 13 Days
To calculate the probability of completion of the activity in 13 days, we need to use the normal distribution formula:
Z = (X - tE) / σ

where,
X = completion time
tE = expected time
σ = standard deviation

Substituting the given values in the above formula, we get:
Z = (13 - 15) / 1.63 = -1.23

Using the Z-table, we can find the probability corresponding to the Z-value of -1.23. The probability is 0.1093.

However, since we are interested in the probability of completion in 13 days OR LESS, we need to find the area under the normal distribution curve to the left of the Z-value of -1.23. This can be done by subtracting the probability from 0.5 (since the total area under the curve is 1):
P(X ≤ 13) = 0.5 + 0.1093 = 0.6093

Therefore, the approximate probability of completion of this activity in 13 days is 0.6093 or 60.93%. Option C is the correct answer.
Explore Courses for Computer Science Engineering (CSE) exam

Top Courses for Computer Science Engineering (CSE)

Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84?
Question Description
Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84? for Computer Science Engineering (CSE) 2024 is part of Computer Science Engineering (CSE) preparation. The Question and answers have been prepared according to the Computer Science Engineering (CSE) exam syllabus. Information about Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84? covers all topics & solutions for Computer Science Engineering (CSE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84?.
Solutions for Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84? in English & in Hindi are available as part of our courses for Computer Science Engineering (CSE). Download more important topics, notes, lectures and mock test series for Computer Science Engineering (CSE) Exam by signing up for free.
Here you can find the meaning of Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84? defined & explained in the simplest way possible. Besides giving the explanation of Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84?, a detailed solution for Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84? has been provided alongside types of Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84? theory, EduRev gives you an ample number of questions to practice Time estimates of an activity in a PERT network are: Optimistic time to = 9 days; pessimistic time tp = 21 days and most likely time te = 15 days. The approximates probability of completion of this activity in 13 days is: Ops: A. 0.16 B. 0.34 C. 0.5 D. 0.84? tests, examples and also practice Computer Science Engineering (CSE) tests.
Explore Courses for Computer Science Engineering (CSE) exam

Top Courses for Computer Science Engineering (CSE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev