Computer Science Engineering (CSE) Exam  >  Computer Science Engineering (CSE) Questions  >  Delay in the activity which is on the noncrit... Start Learning for Free
Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time?
Most Upvoted Answer
Delay in the activity which is on the noncritical path Ops: A. would n...
Explanation:

In project management, there are two types of paths, critical path, and non-critical path. The critical path is the longest path in a project network diagram and determines the shortest time to complete the project. Any delay in the critical path will increase the project completion time. On the other hand, the non-critical path is the path that does not affect the project's completion time.

Delay in Non-Critical Path

When there is a delay in the non-critical path, it may or may not affect the project's completion time depending upon the amount of delay.

Scenario A: Would not increase completion time of the project

If there is a delay in the non-critical path, and the delay is within the free slack, then it would not affect the project's completion time. The free slack is the amount of time a non-critical activity can be delayed without delaying the project's completion time.

Scenario B: Would increase project completion time, If the amount of delay greater than free slack

If there is a delay in the non-critical path, and the delay is greater than the free slack, then it would increase the project's completion time. The project manager needs to analyze the impact of the delay and take necessary actions to minimize the delay.

Scenario C: Would increase the project completion time, if the amount of delay exceeds total slack

If there is a delay in the non-critical path, and the delay exceeds the total slack, then it would increase the project's completion time. The total slack is the amount of time an activity can be delayed without delaying the project's completion time beyond the target completion date.

Scenario D: Would increase the project completion time

In summary, any delay in the non-critical path, beyond the free slack, will increase the project completion time, and the delay needs to be managed efficiently. The project manager needs to identify the impact of the delay, analyze the critical path, and take necessary actions to minimize the delay.
Explore Courses for Computer Science Engineering (CSE) exam

Top Courses for Computer Science Engineering (CSE)

Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time?
Question Description
Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time? for Computer Science Engineering (CSE) 2024 is part of Computer Science Engineering (CSE) preparation. The Question and answers have been prepared according to the Computer Science Engineering (CSE) exam syllabus. Information about Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time? covers all topics & solutions for Computer Science Engineering (CSE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time?.
Solutions for Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time? in English & in Hindi are available as part of our courses for Computer Science Engineering (CSE). Download more important topics, notes, lectures and mock test series for Computer Science Engineering (CSE) Exam by signing up for free.
Here you can find the meaning of Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time? defined & explained in the simplest way possible. Besides giving the explanation of Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time?, a detailed solution for Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time? has been provided alongside types of Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time? theory, EduRev gives you an ample number of questions to practice Delay in the activity which is on the noncritical path Ops: A. would not increase completion time of the project B. would increase project completion time, If the amount of delay greater than free slack C. would increase the project completion time, if amount of delay exceeds total slack D. would increase the project completion time? tests, examples and also practice Computer Science Engineering (CSE) tests.
Explore Courses for Computer Science Engineering (CSE) exam

Top Courses for Computer Science Engineering (CSE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev