Question Description
Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer? for GMAT 2024 is part of GMAT preparation. The Question and answers have been prepared
according to
the GMAT exam syllabus. Information about Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for GMAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer?.
Solutions for Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for GMAT.
Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice Machine X can complete a job in half the time it takes Machine Y to complete the same job, and Machine Z takes 50% longer than Machine X to complete the job. If all three machines always work at their respective, constant rates, what is the ratio of the amount of time it will take Machines X and Z to complete the job to the ratio of the amount of time it will take Machines Y and Z to complete the job?a)5 to 1b)10 to 7c)1 to 5d)7 to 10e)9 to 10Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice GMAT tests.