If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?
  • a)
    4 (1/60)
  • b)
    5
  • c)
    5 (5/11)
  • d)
    5 (1/2)
  • e)
    11
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
If it would take one machine 10 minutes to fill a large production ord...
Let the total production order be of 60 units
1st machine can fill the production order at 6 units per minute
2nd machine can fill the production order at 5 units per minute
So, 1st  and 2nd machine working togather can fill the production order at 11 units per minute.
The total production order is of 60 units so the time taken to complete the order is  minutes
Hence answer is (C) ,
Attention GMAT Students!
To make sure you are not studying endlessly, EduRev has designed GMAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in GMAT.
Explore Courses for GMAT exam

Similar GMAT Doubts

Top Courses for GMAT

If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer?
Question Description
If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer? for GMAT 2024 is part of GMAT preparation. The Question and answers have been prepared according to the GMAT exam syllabus. Information about If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for GMAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer?.
Solutions for If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for GMAT. Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer?, a detailed solution for If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If it would take one machine 10 minutes to fill a large production order and another machine 12 minutes to fill the same order, how many minutes would it take both machines working together, at their respective rates, to fill the order?a)4 (1/60)b)5c)5 (5/11)d)5 (1/2)e)11Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice GMAT tests.
Explore Courses for GMAT exam

Top Courses for GMAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev