Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer? for GMAT 2024 is part of GMAT preparation. The Question and answers have been prepared
according to
the GMAT exam syllabus. Information about Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer? covers all topics & solutions for GMAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer?.
Solutions for Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer? in English & in Hindi are available as part of our courses for GMAT.
Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer?, a detailed solution for Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer? has been provided alongside types of Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice Machine J runs at a constant rate and produces a lot consisting of 300 bottles in 4 hours. How much less time would it take to produce the lot of cans if both machines J and P were run simultaneously?(1) Machine J produces lots faster than machine P.(2) Machine J and machine P finish at least 3 lots in 3 hours working simultaneously.a)Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient to answer the question askedb)Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient to answer the question askedc)BOTH statements (1) and (2) TOGETHER are sufficient to answer the question asked, but NEITHER statement ALONE is sufficientd)EACH statement ALONE is sufficient to answer the question askede)Statements (1) and (2) TOGETHER are NOT sufficient to answer the question asked, and additional data are neededCorrect answer is option 'E'. Can you explain this answer? tests, examples and also practice GMAT tests.