Electrical Engineering (EE) Exam  >  Electrical Engineering (EE) Questions  >  Consider the following statements related to ... Start Learning for Free
Consider the following statements related to Project Phases:
1. In sequential relationship next phase can start if and only if previous phase is complete.
2. Sequential relationship allows a project manager to reduce the project completion time.
3. In overlapping phase relationship next phase can begin before the completion of previous phase.
4. Overlapping phase is a risk free phase as all phase can be work independently.
Which of the following statements are correct?
  • a)
    Only 1 and 2
  • b)
    3 and 4
  • c)
    Only 2 and 4
  • d)
    Only 1 and 3
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Consider the following statements related to Project Phases:1. In sequ...
Sequential and Overlapping Project Phases

Sequential Relationship:
1. In a sequential relationship, the next phase of a project can only begin once the previous phase is complete.
2. This relationship ensures that there is a clear order and dependency between the project phases.
3. It helps in maintaining a structured approach to project execution.
4. Sequential relationship does not necessarily reduce the project completion time, as each phase needs to be completed before the next one can start.

Overlapping Relationship:
1. In an overlapping relationship, the next phase of a project can begin before the completion of the previous phase.
2. Overlapping phases allow for parallel execution and can potentially reduce the project completion time.
3. This relationship requires careful planning and coordination to ensure that the overlapping phases do not interfere with each other.
4. Overlapping phases introduce a certain level of risk as there is a possibility of conflicts or dependencies between the concurrent activities.

Correct Statements:
Based on the given statements, the correct statements are:

1. In sequential relationship next phase can start if and only if the previous phase is complete.
This statement is correct as it defines the fundamental characteristic of a sequential project phase relationship. The completion of one phase is required before the next phase can begin.

3. In overlapping phase relationship next phase can begin before the completion of the previous phase.
This statement is correct as it describes the nature of an overlapping project phase relationship. Overlapping phases allow for concurrent execution and can provide opportunities for reducing project completion time.

Explanation of Incorrect Statements:
2. Sequential relationship allows a project manager to reduce the project completion time.
This statement is incorrect. A sequential relationship does not inherently reduce the project completion time. It ensures a structured approach to project execution but does not allow for concurrent activities.

4. Overlapping phase is a risk-free phase as all phases can work independently.
This statement is incorrect. Overlapping phases introduce a certain level of risk as there is a possibility of conflicts or dependencies between the concurrent activities. Proper planning and coordination are required to minimize these risks.

In conclusion, statements 1 and 3 are the correct statements regarding project phases. Sequential relationship ensures that the next phase can only start after the completion of the previous phase, while overlapping relationship allows for concurrent execution of phases to potentially reduce project completion time.
Free Test
Community Answer
Consider the following statements related to Project Phases:1. In sequ...
Phase to Phase Relationship:
Sequential Relationship:
  • In sequential relationship next phase can start if and only if previous phase is complete.
  • Traditionally construction projects generally use sequential relationship.
  • Step by step nature of this approach reduces uncertainty but also eliminates options for shortening the schedule.
Overlapping Relationship:
  • In overlapping phase relationship next phase can begin before the completion of previous phase.
  • This technique allows schedule compression called fast tracking.
  • This technique can lead to increase in risk and may result in rework if a subsequent phase progress before accurate information is available from previous phase.
Thus statement 1 and 3 are the correct answer.
Explore Courses for Electrical Engineering (EE) exam

Similar Electrical Engineering (EE) Doubts

Top Courses for Electrical Engineering (EE)

Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer?
Question Description
Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer?.
Solutions for Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements related to Project Phases:1. In sequential relationship next phase can start if and only if previous phase is complete.2. Sequential relationship allows a project manager to reduce the project completion time.3. In overlapping phase relationship next phase can begin before the completion of previous phase.4. Overlapping phase is a risk free phase as all phase can be work independently.Which of the following statements are correct?a)Only 1 and 2b)3 and 4c)Only 2 and 4d)Only 1 and 3Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev