A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can A working alone complete 60% of the work?
  • a)
    70
  • b)
    110
  • c)
    80
  • d)
    105
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
A and B together can do a piece of work in 50 days. If A is 40% less e...
Given:
A and B together can do a piece of work in 50 days.
A is 40% less efficient than B
Concept used:
Total work = Efficiency of the workers × time taken by them
Calculation:
Let the efficiency of B be 5a
So, efficiency of A = 5a × 60%
⇒ 3a
So, total efficiency of them = 8a
Total work = 8a × 50
⇒ 400a
Now,
60% of the work = 400a × 60%
⇒ 240a
Now,
Required time = 240a/3a
⇒ 80 days
∴ A can complete 60% of the work working alone in 80 days.
Free Test
Community Answer
A and B together can do a piece of work in 50 days. If A is 40% less e...
To solve this problem, let's assume that B can complete the work in x days.

Efficiency of A = 100% - 40% = 60% of B.

Let's calculate the efficiency of A and B:

Efficiency of A = 60% of B = (60/100) * B = 0.6B

Efficiency of B = B

Now, let's calculate the work done by A and B in one day:

Work done by A in one day = Efficiency of A * 1 day = 0.6B * 1 = 0.6B

Work done by B in one day = Efficiency of B * 1 day = B * 1 = B

Working together, A and B can complete the work in 50 days. So, in one day, they can complete 1/50th of the work.

Work done by A and B together in one day = 1/50th of the work

Adding the work done by A and B in one day, we get:

0.6B + B = 1/50

Simplifying the equation, we have:

1.6B = 1/50

Dividing both sides by 1.6, we get:

B = 1/50 * 1/1.6

B = 1/80

So, B can complete 1/80th of the work in one day.

Now, let's calculate the number of days it takes for A to complete 60% of the work:

Work done by A in one day = 0.6B

Substituting the value of B, we have:

Work done by A in one day = 0.6 * 1/80 = 1/133.33

To complete 60% of the work, A would require:

(60/100) * (1/133.33) = 1/222.22

So, A working alone can complete 1/222.22 of the work in one day.

To find the number of days required to complete 60% of the work, we divide 1 by 1/222.22:

1 / (1/222.22) = 222.22

Therefore, A working alone can complete 60% of the work in approximately 222.22 days.

However, none of the given options match this answer. So, it seems that there may be an error in the question or options provided.
Explore Courses for Banking Exams exam

Similar Banking Exams Doubts

A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer?
Question Description
A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer?.
Solutions for A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer?, a detailed solution for A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B together can do a piece of work in 50 days. If A is 40% less efficient than B, in how many days can Aworking alone complete 60% of the work?a)70b)110c)80d)105Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev