50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?
  • a)
    194
  • b)
    159
  • c)
    160
  • d)
    195
  • e)
    183
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
50 people can complete a work in 20 days. A contractor has employed 35...
Total work = 50 x 20 = 1000 units of man days
Work done by 12 people in 35 days = 35 x 12 = 420 man days
Remaining work = 1000 - 420 = 580 man days
Let the number of people to be added be N.
Therefore, (N+35) x 3 = 580
N+35 = 580/3
N+35 = 193.33 = 194 people (people have to be an integral number)
Or N = 159 people
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer?
Question Description
50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer?.
Solutions for 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer?, a detailed solution for 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 50 people can complete a work in 20 days. A contractor has employed 35 people to complete the work. However after 12 days he gets a notice that he has to complete the remaining work within 3 days. Then how many more people does he have to employ to finish the work on time?a)194b)159c)160d)195e)183Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev