CA Foundation Exam  >  CA Foundation Questions  >  A fair and genuine pre-estimated sum of damag... Start Learning for Free
A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed as 
  • a)
    Liquidated Damages
  • b)
    Ordinary damages
  • c)
    Penalty 
  • d)
    None of the above.
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
A fair and genuine pre-estimated sum of damages likely to result due t...
Answer:

The fair and genuine pre-estimated sum of damages likely to result due to a breach of contract is termed as Liquidated Damages. This concept is widely used in contract law to provide a reasonable estimate of damages that may occur in the event of a breach, especially when it is difficult to ascertain the actual loss suffered by the aggrieved party.

Explanation:

1. Liquidated Damages:
Liquidated damages are a specific amount of money agreed upon by the parties to a contract, which will be paid as compensation in the event of a breach. These damages are typically specified in the contract itself, either as a fixed amount or as a formula for calculation.

2. Purpose of Liquidated Damages:
The purpose of including liquidated damages in a contract is to provide certainty and avoid the need for lengthy and costly litigation to determine the actual damages suffered by the non-breaching party. It allows the parties to agree on a reasonable estimate of damages in advance, based on their understanding of the potential harm caused by a breach.

3. Enforceability:
In order for liquidated damages to be enforceable, certain conditions must be met. These include:

- The damages must be difficult to ascertain at the time of contract formation.
- The amount must be a reasonable estimate of the anticipated damages.
- The damages must not be excessive or punitive in nature.
- The liquidated damages clause must be a genuine pre-estimate of loss and not a penalty.

4. Difference between Liquidated Damages and Penalty:
The key difference between liquidated damages and a penalty is that a penalty is designed to punish the breaching party, while liquidated damages are intended to compensate the non-breaching party for the actual loss suffered. If a provision in a contract is found to be a penalty, it will not be enforceable.

Conclusion:
In conclusion, a fair and genuine pre-estimated sum of damages likely to result due to a breach of contract is termed as liquidated damages. It provides a reasonable estimate of damages in advance, based on the understanding of the potential harm caused by a breach. However, it is important to ensure that the liquidated damages clause meets the necessary conditions for enforceability and is not considered a penalty.
Explore Courses for CA Foundation exam
A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer?
Question Description
A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer? for CA Foundation 2024 is part of CA Foundation preparation. The Question and answers have been prepared according to the CA Foundation exam syllabus. Information about A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for CA Foundation 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer?.
Solutions for A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CA Foundation. Download more important topics, notes, lectures and mock test series for CA Foundation Exam by signing up for free.
Here you can find the meaning of A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer?, a detailed solution for A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A fair and genuine pre-estimated sum of damages likely to result due to breach of contract is termed asa)Liquidated Damagesb)Ordinary damagesc)Penaltyd)None of the above.Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice CA Foundation tests.
Explore Courses for CA Foundation exam

Top Courses for CA Foundation

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev