A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103 MW hr. Calculate load factor.
  • a)
    0.40
  • b)
    0.96
  • c)
    0.57
  • d)
    0.39
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
A generating station has a maximum demand of 80 MW and connected Load ...
The load factor percentage is derived by dividing the total kilowatt-hours (kWh) consumed in a designated period by the product of the maximum demand in kilowatts (kW) and the number of hours in the period.
Maximum demand = 80 MW
Connected load = 150 MW
Units generated in one year = 400 × 103 MW hr
Total number of hours in a year = 8760
Average load = (400x103)8760
= 45.662 MW
Load Factor = Average load/Maximum demand 
= 45.662/80
= 0.57
Free Test
Community Answer
A generating station has a maximum demand of 80 MW and connected Load ...

Calculation of Load Factor:

Load Factor is defined as the average load divided by the maximum demand. It is a measure of how efficiently a generating station is being utilized over a specific period of time.

Given data:
- Maximum demand = 80 MW
- Connected Load = 150 MW
- Energy generated in a year = 400 × 10^3 MW hr

Calculation:
- Average Load = Energy generated in a year / Total hours in a year
- Average Load = 400 × 10^3 MW hr / 8760 hr (assuming 1 year = 8760 hours)
- Average Load = 45.66 MW

Load Factor = Average Load / Maximum Demand
Load Factor = 45.66 MW / 80 MW
Load Factor ≈ 0.57

Therefore, the Load Factor for the generating station is approximately 0.57. Hence, the correct answer is option 'C'.
Explore Courses for RRB NTPC/ASM/CA/TA exam

Top Courses for RRB NTPC/ASM/CA/TA

A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer?
Question Description
A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer? for RRB NTPC/ASM/CA/TA 2024 is part of RRB NTPC/ASM/CA/TA preparation. The Question and answers have been prepared according to the RRB NTPC/ASM/CA/TA exam syllabus. Information about A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for RRB NTPC/ASM/CA/TA 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer?.
Solutions for A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for RRB NTPC/ASM/CA/TA. Download more important topics, notes, lectures and mock test series for RRB NTPC/ASM/CA/TA Exam by signing up for free.
Here you can find the meaning of A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer?, a detailed solution for A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A generating station has a maximum demand of 80 MW and connected Load of 150 MW hr generated in a year are 400 × 103MW hr. Calculate load factor.a)0.40b)0.96c)0.57d)0.39Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice RRB NTPC/ASM/CA/TA tests.
Explore Courses for RRB NTPC/ASM/CA/TA exam

Top Courses for RRB NTPC/ASM/CA/TA

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev