Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.
  • a)
    Ej – Li - D (i, j)
  • b)
    Lj – Ei - D (i, j)
  • c)
    Lj – Ej - D (i, j)
  • d)
    Ej - Ei
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
Independent float of an activity (i, j) is denoted by IF (i, j). The e...
Float:
  • Float indicates the time by which, starting or finishing of an activity can be delayed without completion time.
  • Float is associated with an activity and is analogous to the term slack.
Independent Float:
  • It is the amount of time by which an activity can be delayed when all the preceding activities are completed as late as possible and all succeeding activities started as early as possible.
  • Independent float can also be defined as the excess of minimum available time over the required activity duration.
  • Consider a partial network as below
  • If activity c-d is under consideration, and activity b-c finishes as its latest possible time TcL and succeeding activity j-k start at its earliest time TiE.
  • Then activity i-j can take up any duration from t" to ( TT) without affecting any activity of the project.
  • The difference between (TjE-TiL) and t is known as Independent float for activity i-j Independent float for i-j,

​Solution:
FID = (TjE - TiL) - tij
FID = Ej – Li - D (i, j)
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer?
Question Description
Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity.a)Ej – Li - D (i, j)b)Lj – Ei - D (i, j)c)Lj – Ej - D (i, j)d)Ej - EiCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev