Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  What is the main limitation of bar chart?a)It... Start Learning for Free
What is the main limitation of bar chart?
  • a)
    It does not help in material and labour planning.
  • b)
    It does not show all the activities of a project.
  • c)
    It does not indicate critical activities of a projects.
  • d)
    Project duration cannot be estimated.
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
What is the main limitation of bar chart?a)It does not help in materia...
Bar chart (Gantt chart):
(i) It is a pictorial chart.
(ii) It has two coordinate axes, the horizontal coordinate represents the elapsed time and the vertical coordinate represents the job or activity to be performed.
(iii) The beginning and end of each bar represent starting and finishing times of a particular activity respectively.
(iv) The length of the bar shows the time required for completion.
Limitation of a bar chart:
(i) Lack of degree of detail.
(ii) A bar chart does not show the progress of work and hence it can not be used as a control device.
(iii) A bar chart is unable to depict the interdependencies of various activities clearly.
(iv) No provision to account for time uncertainties.
(v) Bar chart can not distinguish between critical and non-critical activities and hence resource smoothening and resource leveling can not be done.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer?
Question Description
What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer?.
Solutions for What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer?, a detailed solution for What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice What is the main limitation of bar chart?a)It does not help in material and labour planning.b)It does not show all the activities of a project.c)It does not indicate critical activities of a projects.d)Project duration cannot be estimated.Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev