Class 7 Exam  >  Class 7 Questions  >  12 men can finish our work in 10 days how man... Start Learning for Free
12 men can finish our work in 10 days how many more man are needed to complete the work in six days?
Most Upvoted Answer
12 men can finish our work in 10 days how many more man are needed to ...
Given Information:

- 12 men can finish a work in 10 days

Calculating Work Rate:

To find out how many more men are needed to complete the work in six days, we need to calculate the work rate of the 12 men.

- Let's assume that the total work is denoted by "W".
- Since 12 men can complete the work in 10 days, the work rate of the 12 men is given by W/10.

Calculating the Total Work:

- The total work can be calculated by multiplying the work rate of the 12 men by the number of days it takes them to complete the work.
- So, the total work is equal to (W/10) x 10 = W.

Calculating the Work Rate for 6 Days:

- To calculate the work rate for 6 days, we divide the total work by the number of days.
- So, the work rate for 6 days is given by W/6.

Calculating the Number of Men Required:

- Let's assume that the number of additional men required is denoted by "x".
- The total work done by the additional men in 6 days is given by (W/6) x 6 = W.
- Since the work rate of each man is W/6, the total work done by x men in 6 days is given by (W/6) x x.

Equating the Work Done:

- The total work done by the 12 men and the additional x men should be equal to the total work.
- So, we have the equation (W/10) x 10 + (W/6) x x = W.

Simplifying the Equation:

- Simplifying the equation, we get 12W/10 + xW/6 = W.
- Multiplying both sides of the equation by 30 to eliminate the denominators, we get 12W x 3 + xW x 5 = 30W.
- Simplifying further, we get 36W + 5xW = 30W.
- Subtracting 30W from both sides, we get 6W + 5xW = 0.

Solving for x:

- Combining like terms, we have 11xW = -6W.
- Dividing both sides by -6W, we get 11x = -6.
- Dividing both sides by 11, we get x = -6/11.

Conclusion:

- Since the number of men cannot be negative, we cannot complete the work in 6 days by adding more men.
- In fact, we would need to remove some men to complete the work in a shorter time.
- Therefore, we cannot determine the exact number of additional men required to complete the work in six days.
Attention Class 7 Students!
To make sure you are not studying endlessly, EduRev has designed Class 7 study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Class 7.
Explore Courses for Class 7 exam

Top Courses for Class 7

12 men can finish our work in 10 days how many more man are needed to complete the work in six days?
Question Description
12 men can finish our work in 10 days how many more man are needed to complete the work in six days? for Class 7 2024 is part of Class 7 preparation. The Question and answers have been prepared according to the Class 7 exam syllabus. Information about 12 men can finish our work in 10 days how many more man are needed to complete the work in six days? covers all topics & solutions for Class 7 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 12 men can finish our work in 10 days how many more man are needed to complete the work in six days?.
Solutions for 12 men can finish our work in 10 days how many more man are needed to complete the work in six days? in English & in Hindi are available as part of our courses for Class 7. Download more important topics, notes, lectures and mock test series for Class 7 Exam by signing up for free.
Here you can find the meaning of 12 men can finish our work in 10 days how many more man are needed to complete the work in six days? defined & explained in the simplest way possible. Besides giving the explanation of 12 men can finish our work in 10 days how many more man are needed to complete the work in six days?, a detailed solution for 12 men can finish our work in 10 days how many more man are needed to complete the work in six days? has been provided alongside types of 12 men can finish our work in 10 days how many more man are needed to complete the work in six days? theory, EduRev gives you an ample number of questions to practice 12 men can finish our work in 10 days how many more man are needed to complete the work in six days? tests, examples and also practice Class 7 tests.
Explore Courses for Class 7 exam

Top Courses for Class 7

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev