If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) days

How did we derive this?
Most Upvoted Answer
If A and B together can finish a certain work in ‘a’ days. They worked...


Explanation of Derivation:

Given Information:
- A and B together can finish a work in 'a' days
- They worked together for 'b' days
- A finished the rest of the work in 'd' days
- Total time taken by A alone to complete the work = ad / (a - b) or bd / (a - b) days

Derivation Steps:

1. Let the total work be represented as 1 unit.
2. A and B together can finish the work in 'a' days, so their combined rate of work is 1/a.
3. They worked together for 'b' days, so the work completed in 'b' days is (b/a) units.
4. The remaining work to be completed by A alone is (1 - b/a) = ((a - b)/a) units.
5. A finishes the remaining work in 'd' days, so A's rate of work is 1/d.
6. Using the formula: Time = Work / Rate, we have Time taken by A alone = (1 - b/a) / 1/d = ((a - b)/a) * d = ad / a - b.
7. Similarly, the time taken by B alone can be calculated by substituting B's rate of work (1 - 1/a) and solving the equation, which results in bd / a - b days.

Therefore, the total time taken by A or B alone to complete the work is ad / (a - b) or bd / (a - b) days, as derived.
Attention GMAT Students!
To make sure you are not studying endlessly, EduRev has designed GMAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in GMAT.
Explore Courses for GMAT exam

Top Courses for GMAT

If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this?
Question Description
If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this? for GMAT 2024 is part of GMAT preparation. The Question and answers have been prepared according to the GMAT exam syllabus. Information about If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this? covers all topics & solutions for GMAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this?.
Solutions for If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this? in English & in Hindi are available as part of our courses for GMAT. Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this? defined & explained in the simplest way possible. Besides giving the explanation of If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this?, a detailed solution for If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this? has been provided alongside types of If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this? theory, EduRev gives you an ample number of questions to practice If A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then ‘B’ (or A) left the work. A (or B) finished the rest of work in ‘d’ days, then, the total time taken by A (or B) alone to complete the work = ad / (a – b) or bd / (a – b) daysHow did we derive this? tests, examples and also practice GMAT tests.
Explore Courses for GMAT exam

Top Courses for GMAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev