CAT Exam  >  CAT Questions  >  The table below shows the series of activitie... Start Learning for Free
The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.
At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?
    Correct answer is '10'. Can you explain this answer?
    Verified Answer
    The table below shows the series of activities that are required to co...
    At the end of the 13ttl day, the following activities can be completed are A, B, C, D, E, F, G, H, N and J; i.e. a total of 10 activities.
    Answer: 10
    This question is part of UPSC exam. View all CAT courses
    Explore Courses for CAT exam

    Top Courses for CAT

    The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer?
    Question Description
    The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer?.
    Solutions for The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
    Here you can find the meaning of The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer?, a detailed solution for The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer? has been provided alongside types of The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.At the end of the 13 th day, what can be the maximum number of scheduled activities that can be completed?Correct answer is '10'. Can you explain this answer? tests, examples and also practice CAT tests.
    Explore Courses for CAT exam

    Top Courses for CAT

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev