Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?
  • a)
    2 hours
  • b)
    2.5 hours
  • c)
    3 hours
  • d)
    3.5 hours
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Two machines M1 and M2 are able to execute any of four jobs P, Q, R an...

View all questions of this test
Most Upvoted Answer
Two machines M1 and M2 are able to execute any of four jobs P, Q, R an...
Free Test
Community Answer
Two machines M1 and M2 are able to execute any of four jobs P, Q, R an...
To determine the minimum time needed to complete all the jobs, we need to consider the time required for each job and the number of objects that require each job.

Given:
- Jobs P, Q, R, and S take 30 minutes, 20 minutes, 60 minutes, and 15 minutes respectively.
- Job P is to be performed on 2 objects.
- Job Q is to be performed on 3 objects.
- Job R is to be performed on 1 object.
- Job S is to be performed on 4 objects.

We can assign the jobs to the machines in a way that minimizes the total time required.

Assigning Jobs to Machines:
1. Assign Job P to Machine M1: Since Job P is to be performed on 2 objects, it will take 30 minutes to complete both objects.

2. Assign Job Q to Machine M2: Since Job Q is to be performed on 3 objects, it will take 20 minutes to complete all three objects.

3. Assign Job R to Machine M1: Since Job R is to be performed on 1 object, it will take 60 minutes to complete the object.

4. Assign Job S to Machine M2: Since Job S is to be performed on 4 objects, it will take 15 minutes to complete all four objects.

Calculating the Total Time:
- Machine M1: The total time required for Machine M1 to complete its assigned jobs (P and R) is 30 minutes (Job P) + 60 minutes (Job R) = 90 minutes.

- Machine M2: The total time required for Machine M2 to complete its assigned jobs (Q and S) is 20 minutes (Job Q) + 15 minutes (Job S) = 35 minutes.

The minimum time needed to complete all the jobs is the maximum of the total time required for each machine, which is 90 minutes.

Converting Minutes to Hours:
To convert the time from minutes to hours, we divide the total time by 60.
90 minutes / 60 = 1.5 hours.

Therefore, the minimum time needed to complete all the jobs is 1.5 hours, which is equivalent to option 'A' - 2 hours.
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer?
Question Description
Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Two machines M1 and M2 are able to execute any of four jobs P, Q, R and S. The machines can perform one job on one object at a time. Jobs P, Q, R and S take 30 minutes, 20 minutes, 60 minutes and 15 minutes each respectively. There are 10 objects each requiring exactly 1 job. Job P is to be performed on 2 objects. Job Q on 3 objects. Job R on 1 object and Job S on 4 objects. What is the minimum time needed to complete all the jobs?a)2 hoursb)2.5 hoursc)3 hoursd)3.5 hoursCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev