The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be: 
  • a)
    11    
  • b)
    13    
  • c)
    18  
  • d)
    24
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
The earliest occurrence time for event '1' is 8 weeks and the ...
Total float = 37 – 8 – 11 = 18 days. 
View all questions of this test
Most Upvoted Answer
The earliest occurrence time for event '1' is 8 weeks and the ...
The total float is the amount of time that an activity can be delayed without delaying the project's completion time. To calculate the total float, we need to consider the earliest and latest occurrence times for both events and the activity time.

Given:
- Event 1: earliest occurrence time = 8 weeks, latest occurrence time = 26 weeks
- Event 2: earliest occurrence time = 32 weeks, latest occurrence time = 37 weeks
- Activity time = 11 weeks

Calculating the earliest start time for the activity:
The earliest start time for the activity is the maximum of the earliest occurrence times for both events. Therefore, the earliest start time = max(8 weeks, 32 weeks) = 32 weeks.

Calculating the latest start time for the activity:
The latest start time for the activity is the minimum of the latest occurrence times for both events minus the activity time. Therefore, the latest start time = min(26 weeks, 37 weeks) - 11 weeks = 26 weeks - 11 weeks = 15 weeks.

Calculating the total float:
The total float is the difference between the latest start time and the earliest start time for the activity. Therefore, the total float = latest start time - earliest start time = 15 weeks - 32 weeks = -17 weeks.

Explanation and Conclusion:
The negative value for the total float (-17 weeks) indicates that the activity cannot be delayed without delaying the project's completion time. In other words, there is no float available for the activity. However, it is important to note that this negative value does not make sense in the context of project scheduling, as float is typically a positive value representing the flexibility in scheduling.

Therefore, the given information is inconsistent or incorrect, as it is not possible to calculate a valid total float based on the provided data.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer?
Question Description
The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer?.
Solutions for The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer?, a detailed solution for The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be:a)11 b)13 c)18 d)24Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev