If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to: 
  • a)
    18 weeks  
  • b)
    14 weeks  
  • c)
    56 weeks  
  • d)
    40 weeks 
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
If the earliest starting time for an activity is 8 weeks, the latest f...
T.F. = LSi− ESij − tij = 37 − 8 − 11 = 18
View all questions of this test
Most Upvoted Answer
If the earliest starting time for an activity is 8 weeks, the latest f...
The total float of an activity in project management refers to the amount of time that an activity can be delayed without impacting the project's overall schedule. To calculate the total float, we need to subtract the earliest starting time (EST) and the duration time of the activity from the latest finish time (LFT).

Given information:
- Earliest starting time (EST) = 8 weeks
- Latest finish time (LFT) = 37 weeks
- Duration time of the activity = 11 weeks

Calculating the total float:
Total float = LFT - (EST + Duration time)

Substituting the given values into the formula, we have:

Total float = 37 weeks - (8 weeks + 11 weeks)
Total float = 37 weeks - 19 weeks
Total float = 18 weeks

Therefore, the total float for this activity is 18 weeks.

Explanation:
The earliest starting time (EST) represents the earliest point in time that the activity can begin, while the latest finish time (LFT) represents the latest point in time that the activity can be completed without delaying the project. The duration time of the activity is the time required to complete the activity.

To calculate the total float, we subtract the earliest starting time and the duration time from the latest finish time. The result represents the amount of time that the activity can be delayed without affecting the project's schedule.

In this case, the earliest starting time is 8 weeks, the latest finish time is 37 weeks, and the duration time of the activity is 11 weeks. By substituting these values into the formula, we find that the total float is equal to 18 weeks.

This means that the activity can be delayed by up to 18 weeks without impacting the overall project schedule. Any delay beyond this would cause a delay in the project's completion.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer?
Question Description
If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer?.
Solutions for If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to:a)18 weeks b)14 weeks c)56 weeks d)40 weeksCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev