The net requirements of an item over 5 consecutive weeks are 50-015-20...
The Least Unit Cost Technique
The Least Unit Cost Technique is a method used to determine the optimal order quantity and reorder point for inventory management. It considers both the cost of carrying inventory and the cost of placing an order.
To solve this problem, we will use the following formula:
Total cost = Carrying cost + Ordering cost
Given Data:
- Net requirements over 5 consecutive weeks: 50, 15, 20, 20
- Carrying cost per item per week: Re. 1
- Ordering cost per order: Rs. 100
- Starting inventory: 0
Calculating the Optimal Order Quantity:
To determine the optimal order quantity, we need to find the week with the highest net requirement. In this case, it is 50.
The optimal order quantity can be calculated using the formula:
Optimal Order Quantity = (Highest Net Requirement) - (Starting Inventory)
In this case, the optimal order quantity will be 50 - 0 = 50.
Calculating the Optimal Reorder Point:
The reorder point is the inventory level at which an order should be placed. It is determined by considering the lead time (time between placing an order and receiving it) and the average weekly demand.
In this case, we have 5 consecutive weeks of net requirements: 50, 15, 20, 20. The average weekly demand can be calculated by summing up these values and dividing by 5:
Average Weekly Demand = (50 + 15 + 20 + 20) / 5 = 21
The reorder point can be calculated using the formula:
Reorder Point = (Average Weekly Demand) x (Lead Time)
Since the lead time is not given in the problem, we assume it to be 1 week.
Reorder Point = 21 x 1 = 21
Calculating the Total Cost:
To calculate the total cost, we need to consider the carrying cost and the ordering cost for each week.
The carrying cost can be calculated by multiplying the carrying cost per item per week by the inventory level at the end of each week.
The ordering cost is incurred whenever an order is placed. In this case, we only place one order with the optimal order quantity.
Total Cost = (Carrying Cost Week 1 + Carrying Cost Week 2 + Carrying Cost Week 3 + Carrying Cost Week 4 + Carrying Cost Week 5) + Ordering Cost
Carrying Cost Week 1 = (Starting Inventory) x (Carrying cost per item per week) = 0 x Re. 1 = 0
Carrying Cost Week 2 = (Inventory at end of Week 1) x (Carrying cost per item per week) = 50 x Re. 1 = 50
Carrying Cost Week 3 = (Inventory at end of Week 2) x (Carrying cost per item per week) = (50 - 15) x Re. 1 = 35
Carrying Cost Week 4 = (Inventory at end of Week 3) x (Carrying cost per item per week) = (35 - 20) x Re. 1 = 15
Carrying Cost Week 5 = (Inventory at end of Week 4) x (Carrying cost per item per week) = (
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.