Question Description
A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared
according to
the Mechanical Engineering exam syllabus. Information about A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering.
Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A soldering operation was work sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would bea)5 minutesb)12 minutesc)20 minutesd)22 minutesCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.