Question Description
A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared
according to
the Mechanical Engineering exam syllabus. Information about A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering.
Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.