Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:
P. The minimum stripping time for props to slab spanning over 4.5 m is 7 days
Q. The minimum stripping time for props to arches spanning over 6 m is 14 days.
R. To ensure strength of Designed concrete mix, Random sampling procedure is adopted
S. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.
  • a)
    P – True Q – True R – True S – False
  • b)
    P – False Q – False R – True S – True
  • c)
    P – False Q – True R – True S – True
  • d)
    P – False Q – False R – True S – False
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Consider the following statements and Identify the correct option with...
As per IS 456 : 2000,
(i) The minimum stripping time for props to slab spanning up to 4.5 m and spanning over 4.5 m is 7 days and 14 days respectively.
(ii) The minimum stripping time for props to aches spanning up to 6 m and spanning over 6 m is 14 days and 21 days respectively.
(iii) When bar of two different diameter are to be spliced the lap length shall be calculated on the basis of bar of larger diameter.
(iv) A random sampling procedure shall be adopted to ensure that each concrete batch shall have a reasonable chance of being tested that is, the sampling should be spread over the entire period of concreting and cover all mixing units.
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer?
Question Description
Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements and Identify the correct option with regard to provisions of IS 456: 2000:P. The minimum stripping time for props to slab spanning over 4.5 m is 7 daysQ. The minimum stripping time for props to arches spanning over 6 m is 14 days.R. To ensure strength of Designed concrete mix, Random sampling procedure is adoptedS. When bar of two different diameter are to be spliced, the lap length shall be calculated on the basis of bar of the larger diameter.a)P – True Q – True R – True S – Falseb)P – False Q – False R – True S – Truec)P – False Q – True R – True S – Trued)P – False Q – False R – True S – FalseCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev