CLAT Exam  >  CLAT Notes  >  Quantitative Techniques for CLAT  >  Time and Work

Time and Work | Quantitative Techniques for CLAT PDF Download

Introduction 

Work is defined as something which has an effect or outcome; often the one desired or expected. The basic concept of Time and Work is similar to that across all Arithmetic topics, i.e. the concept of Proportionality.

Efficiency is inversely proportional to the Time taken when the amount of work done is constant.

What is Time and Work?

The important terms related to time and work are given below:

  • Time Taken: Rate of work and time are inversely proportional to each other. Thus, R = 1/T
  • Work Done: It takes (T) time to complete a certain amount of work (W). The number of units of work done per unit time. Thus, Work Done (W) = Time (T) * Rate of Work (R)
  • Negative Work: Assume that there are two people A and B who have been assigned to build a table. Here, work refers to the building of a table. Also, assume that there is another person C who is assigned the task of damaging the table. Now, work done by C is termed as negative work as C is effectively lowering the amount of work done by A and B.

Types of Questions from Time and Work

There are some specific types of questions from Time and Work that usually come in exams. Some of the important types of questions from time and work are as follows:

Time and Work | Quantitative Techniques for CLAT

  • Time and Work Questions involving individual efficiencies
    • In such questions, the rates at which some individuals complete work alone are given and you are required to calculate the rate at which they can complete the work together and vice versa.
  • Time and Work Questions involving group efficiencies 
    • Till now, we have looked at problem types where individuals were working, in this type of question, we will now look at problems where people with the same efficiencies are working in groups.

To solve problems on ‘time and work’ the following simple facts should be remembered:

  • If a person can do work in 5 days, then in one day he will do 1/5th of the whole work. Conversely, if a man can do 1/5th of the work in one day, he will complete the whole work in 5 days.
  • If the number of men engaged to do a piece of work be increased in a certain ratio, the time required to do the same work will be decreased in the same ratio and vice versa. Thus if the number of men is changed in the ratio of 3:7, the time required will be changed in the ratio of 7:3.

Time and Work | Quantitative Techniques for CLAT

  • If A is twice as good a workman as B then A will take one-half of the time taken by B to do a certain piece of work.
  • To sum up if M1 persons working T1 hours a day can do W1 work in D1 days and M2 persons working H2 hours a day can do W2 work in D2 days, then the following equation will hold good.
    Time and Work | Quantitative Techniques for CLAT

Example: A does work in 10 days and B does the same work in 15 days. How many days they will take to do the work together.

Solution: A does the work in 10 days, so A’s one-day work = 1/10

B does the work in 15 days, so B’s one day work = 1/15

Work done by A and B in one day = 1/10 + 1/15 = 5/30 = 1/6

Thus, A and B together will be able to finish the work in 6 days.

Example: A builder appoints three construction workers Akash, Sunil and Rakesh on one of his sites. They take 20, 30 and 60 days respectively to do a piece of work. How many days will it take Akash to complete the entire work if he is assisted by Sunil and Rakesh every third day?

Solution: Total work done by Akash, Sunil and Rakesh in 1 day = {(1/20) + (1/30) + (1/60)} = 1/10

Work done along by Akash in 2 days = (1/20) × 2 = 1/10

Work Done in 3 days (1 day of all three together + 2 days of Akash’s work) = (1/10) + (1/10) = 1/5

So, work done in 3 days = 1/5

Time taken to complete the work = 5×3 = 15 days

Example: To complete a piece of work, Samir takes 6 days and Tanvir takes 8 days alone respectively. Samir and Tanvir took Rs.2400 to do this work. When Amir joined them, the work was done in 3 days. What amount was paid to Amir?

Solution: Total work done by Samir and Tanvir = {(1/6) + (1/8)} = 7/24

Work done by Amir in 1 day = (1/3) – (7/24) = 1/24

Amount distributed between each of them =  (1/6) : (1/8) : (1/24) = 4:3:1

Amount paid to Amir = (1/24) × 3 × 2400 = Rs.300

Question for Time and Work
Try yourself: A can finish a work in 18 days and B can finish the same work in 9 days. If they work together, what part of the work will they be able to finish in a day. 
View Solution

Concept of Efficiency

Efficiency denotes the amount of work done by any person in 1 day. We use this concept to compare the quality of a worker, i.e., if a worker is more efficient than any other worker, then we can say he/she can do more work in 1 day as compared to other workers.

  • The ratio of the efficiencies of two workers is proportional to the time taken by them to complete a work.
  • If a worker is less efficient than he/she will take more time to complete the work.
  • If a worker is more efficient than he/she will take less time to complete the work.
  • The number of

Example: A is 3 times as efficient as B. If B alone can complete the work in 12 days, then A alone can complete the work in how many days?

Solution:  According to the question, the ratio of the efficiency of A and B is 3 : 1

We know that the ratio of the efficiency is inversely proportional to the ratio of the time taken

So, the ratio of the time taken by A and B to complete the work will be 1 : 3

Let us assume A alone completes the work in x days and B alone completes the work in 3x days

3x=12

x=4

Therefore, A alone can complete the work in 4 days.

Note: The concept of efficiency is widely used to equate the works of men, women, and children.

Example: Dev completed the school project in 20 days. How many days will Arun take to complete the same work if he is 25% more efficient than Dev? 

Solution: Let the days taken by Arun to complete the work be x

The ratio of time taken by Arun and Dev = 125:100 = 5:4

5:4 :: 20:x

⇒ x = {(4×20) / 5}

⇒ x = 16

Tips and Tricks to Solve 

Tip 1: Work and Wages Concept: Ratio of wages of persons doing work is directly proportional to the ratio of efficiency of the persons.

Tip 2: If A can do a piece of work in 10 days, then in 1 day, A will do 1/10 part of total work.

Tip 3: If A is thrice as good as B, then

  1. In a given amount of time, A will be able to do 3 times the work B does. Ratio of work done by A and B (at the same time) = 3 : 1.
  2. For the same amount of work, B will take thrice the time as much as A takes. Ratio of time taken by A and B (same work done) = 1 : 3.

Tip  4: Efficiency is directly proportional to the work done and Inversely Proportional to the time taken.

Tip  5: The number of days or time required to complete the work by A and B both is equal to the ab/a+b.

Solved Examples

Example 1. A tyre has two punctures. The first puncture alone can empty the tyre in 9 minutes and 2nd puncture alone can empty the tyre in 6 minutes. How long will both the punctures take to flat the tyre. 

Sol. The first puncture takes 9 minutes to flatten the tyre, so first puncture’s one-minute work = 1/ 9  The second puncture takes 6 minutes to flatten that tyre, so second puncture’s one-minute work = 1/6

So work done by both punctures in one minute = 1/9 + 1/6 = 5/18

Thus, both punctures together will take 18/5 minutes to flatten the tyre.

Example 2. A and B together can finish a job in 15 days. If A alone can finish the job in 25 days, in how many days can B alone finish the job. 

Sol. A and B together can finish the job in 15 days, so their one day work = 1/15
A alone can finish the job in 25 days, so A’s one day work = 1/25

B’s one day work =  Time and Work | Quantitative Techniques for CLAT

Thus, B alone can finish the job in 75/2 days.

Example 3.  A and B together can build a house in 25 days. They work together for 15 days and then B goes away. A finishes the rest of the work in 20 days. How long will each take to finish the job working separately?

Sol. A+B can finish the work in 25 days, so one day work = 1/25
They work together for 15 days, so the work done by A+B in 15 days = Time and Work | Quantitative Techniques for CLAT

Remaining job = Time and Work | Quantitative Techniques for CLAT 

To complete 2/5 of work in 20 days, A can complete one work in Time and Work | Quantitative Techniques for CLAT = 50 days

B’s one day work = 1/25 – 1/50 = 1/50    

So B can finish the whole work in 50 days.

Question for Time and Work
Try yourself:
A man can do a job in 5 days but with the help of his son he can do it is 3 days. In what time can the son do it alone. 
View Solution

Example 4.   A can finish a job in 10 days, B in 12 days and C in 10 days. In how many days will they finish the job if they work together. 

Sol. A’s one day work = 1/10

B’s one day work = 1/12

C’s one day work = 1/10

A+B+C’s one day work = 1/10 + 1/12 + 1/10 = (6+5+6)/60 = 17/60

Thus, together they can complete the work in 60/17 days.

The document Time and Work | Quantitative Techniques for CLAT is a part of the CLAT Course Quantitative Techniques for CLAT.
All you need of CLAT at this link: CLAT
57 videos|108 docs|73 tests

Top Courses for CLAT

FAQs on Time and Work - Quantitative Techniques for CLAT

1. What is the basic concept of Time and Work in mathematics?
Ans.The basic concept of Time and Work in mathematics refers to the relationship between the amount of work done and the time taken to complete that work. It involves calculating how long it will take for one or more individuals to complete a task based on their work rates, which is usually expressed in terms of work done per unit of time.
2. What are the different types of questions that can be asked in Time and Work problems?
Ans.Time and Work problems can include various types of questions such as: 1. Individual work rates (how long it takes for one person to complete a task). 2. Combined work rates (how long it takes for multiple individuals to complete a task together). 3. Work done by a group in a specific time period. 4. Problems involving efficiency and productivity. 5. Questions about work done by individuals working alternatively.
3. How is efficiency defined in the context of Time and Work?
Ans.Efficiency in the context of Time and Work refers to the amount of work done in a given time period by an individual or group. It is usually expressed as a ratio of work done to time taken and can be used to compare the productivity of different workers or groups. Higher efficiency means more work is accomplished in less time.
4. What are some tips and tricks to solve Time and Work problems quickly?
Ans.Some tips and tricks to solve Time and Work problems quickly include: 1. Understanding the formula: Work = Rate × Time. 2. Converting all work rates to a common unit for easy calculation. 3. Using the concept of LCM (Least Common Multiple) to find the total time taken when multiple people are working together. 4. Breaking down complex problems into smaller, manageable parts. 5. Practicing with different types of problems to improve speed and accuracy.
5. Can you provide an example of a Time and Work problem and its solution?
Ans.An example of a Time and Work problem is: "If A can complete a work in 10 days and B can do it in 15 days, how long will it take for both A and B to complete the work together?" Solution: A's work rate = 1/10 (work per day), B's work rate = 1/15 (work per day). Combined work rate = 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6. Thus, A and B together can complete the work in 6 days.
57 videos|108 docs|73 tests
Download as PDF
Explore Courses for CLAT exam

Top Courses for CLAT

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

Previous Year Questions with Solutions

,

Time and Work | Quantitative Techniques for CLAT

,

study material

,

Exam

,

past year papers

,

ppt

,

practice quizzes

,

Sample Paper

,

video lectures

,

Extra Questions

,

Summary

,

Semester Notes

,

mock tests for examination

,

Viva Questions

,

Free

,

Important questions

,

Time and Work | Quantitative Techniques for CLAT

,

Objective type Questions

,

shortcuts and tricks

,

MCQs

,

pdf

,

Time and Work | Quantitative Techniques for CLAT

;