All Exams  >   RRB NTPC/ASM/CA/TA  >   Mathematics for RRB NTPC / ASM  >   All Questions

All questions of Time and Work for RRB NTPC/ASM/CA/TA Exam

P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in
  • a)
    30 days
  • b)
    25 days
  • c)
    20 days
  • d)
    15 days
Correct answer is option 'B'. Can you explain this answer?

Let distance between the two places = d km
Let total time taken by faster horse = t hr
⇒ Total time taken by slower horse = (t + 5) hr,
Therefore,
speed of the faster horse = d/t km/hr
speed of the slower horse = d/(t + 5) km/hr 
The two horses meet each other in 3 hour 20 min i.e. in 3(1/3) hr = 10/3 hr
In this time, total distance travelled by both the horses together is d. 
d/(t+5) * 10/3 + d/t * 10/3 = d
⇒ 10/(3(t+5)) + 10/3t = 1
⇒ 10t + 10(t+5) = 3t(t+5)
⇒ 20t + 50 = 3t+ 15t
⇒ 3t− 5t − 50 = 0
⇒ 3t+ 10t − 15t − 50 = 0
⇒ t(3t + 10) − 5(3t + 10) = 0
⇒ (3t + 10)(t − 5) = 0
t = 5 (ignoring -ve value) 
Thus, Total time taken by slower horse = 5 + 5 = 10 hr
So Option B is correct

P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
  • a)
    8/15
  • b)
    7/15
  • c)
    11/15
  • d)
    2/11
Correct answer is option 'A'. Can you explain this answer?

Since P to R is double the distance of P to Q,
Therefore, it is evident that the time taken from P to R and back would be double the time taken from P to Q and back (i.e. double of 6.5 hours = 13 hours).
Since going from P to R takes 9 hours, coming back from R to P would take 4 hours i.e. 139 = 4
So Option A is correct

6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.
  • a)
    4 days
  • b)
    6 days
  • c)
    2 days
  • d)
    8 days
Correct answer is option 'A'. Can you explain this answer?

Let work done by 1 man in 1 day = m and work done by 1 woman in 1 day = b 
Work done by 6 men and 8 women in 1 day = 1/10 
=> 6m + 8b = 1/10
=> 60m + 80b = 1    (1)
Work done by 26 men and 48 women in 1 day = 1/2 
=> 26m + 48b =1/2
=> 52m + 96b = 1    (2)
Solving equation 1 and equation 2. We get m = 1/100 and b = 1/200
Work done by 15 men and 20 women in 1 day 
= 15/100 + 20/200 =1/4
=> Time taken by 15 men and 20 women in doing the work = 4 days

P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
  • a)
    8
  • b)
    5
  • c)
    4
  • d)
    6
Correct answer is option 'D'. Can you explain this answer?

Initial distance = 25 dog leaps
Per-minute dog makes 5 dog leaps and cat makes 6 cat leaps = 3 dog leaps
⇒  Relative speed = 2 dog leaps / minutes
⇒  An initial distance of 25 dog leaps would get covered in 12.5 minutes.
So Option D is correct

Sekar, Pradeep and Sandeep can do a piece of work in 15 days. After all the three worked for 2 days, sekar left. Pradeep and Sandeep worked for 10 more days and Pradeep left. Sandeep worked for another 40 days and completed the work. In how many days can sekar alone complete the work if sandeep can complete it in 75 days?
  • a)
    25 days
  • b)
    20 days
  • c)
    30 days
  • d)
    35 days
  • e)
    15 days
Correct answer is option 'C'. Can you explain this answer?

Assume the total work to be 600 units. (LCM of all the numbers) Then Sandeep’s 1 day work = 8 units.
All three’s 1 day work = 40 units.All work together in the first 2 days
Work done in the first 2 days = 40 × 2 = 80 units
Sandeep alone works during the last 40 days
Work done in the last 40 days = 40 × 8 = 320 units
Remaining work = 600 – (320 + 80) = 200 units
This work is done by pradeep and sandeep in 10 days.
Pradeep and Sandeep together’s 1 day work = 20 units
Sekar’s 1 day work = All three 1 day work – Pradeep and Sandeep together’s 1 day
work = 40 units – 20 units = 20 units
Sekar can do the work of 600 units in 30 days.

Arun can do a certain work in the same time in which Bipasha and Rahul together can do it. If Arun and Bipasha together could do it in 10 days and Rahul alone in 50 days, then Bipasha alone could do it in:
  • a)
    15 days
  • b)
    20 days
  • c)
    25 days
  • d)
    30 days
  • e)
    35 days
Correct answer is option 'C'. Can you explain this answer?

Kavya Saxena answered
Arun, Bipasha and rahul’s 1 day work = 1/10 + 1/50 = 6/50 = 3/25
Arun’s 1 day work = Bipasha + Rahul ‘s 1 day work
2*(Arun’s 1 day work) = 3/25
Arun’s 1 day work = 3/50
Bipasha’s 1 day work = 1/10 – 3/50 = 2/50 = 1/25

Efficiency of A is 25% more then B and B takes 25 days to complete a piece of work. A started a work alone and then B joined her 5 days before actual completion of the work. For how many days A worked alone?
  • a)
    9
  • b)
    11
  • c)
    10
  • d)
    25
  • e)
    12
Correct answer is option 'B'. Can you explain this answer?

Efficiency (A : B) = 5 : 4
Number of days(A : B) = 4x : 5x = 4x : 25
∴ Number of days required by A to finish the work alone = 4x
= 4 x 5 = 20.
A and B work together for last 5 days = 5 x 9 = 45%
Efficiency of A = 5% and B’s efficiency = 4%
∴ No. of days taken by A to complete 55% work = 55/5 = 11days

Chetan is thrice as efficient as Mamta and together they can finish a piece of work in 60 days. Mamta will take how many days to finish this work alone?
  • a)
    80
  • b)
    160
  • c)
    240
  • d)
    320
Correct answer is option 'C'. Can you explain this answer?

  • Chetan is thrice as efficient as Mamta.
  • Let, Mamta takes 3x days and Chetan takes x days to complete the work.
  • ∴ 1/x + 1/3x = 1/60 ⇒ x = 80.
  • ∴ Mamta will take 80 × 3 = 240 days to complete the work.

Sruthi, Swetha and Swati together can cut 216 Apples of the same size in 3 hours. Number of Apples cut by Sruthi in 9 hours is same as the number of Apples cut by Swati in 7 hours. In one hour, Swati can cut as many Apples more than Swetha as Swetha can cut more than Sruthi.Then the number of Apples cut by Swetha in one hour?
  • a)
    21
  • b)
    24
  • c)
    27
  • d)
    29
  • e)
    None
Correct answer is option 'B'. Can you explain this answer?

Aruna Singh answered
 
Let's denote:
  • Sruthi's efficiency as 'S' apples/hour
  • Swetha's efficiency as 'W' apples/hour
  • Swati's efficiency as 'T' apples/hour
Given information:
  1. S * 9 = T * 7 => S = (7/9)T
  2. T - W = W - S => T = 2W - S
Total work done in 3 hours:
  • (S + W + T) * 3 = 216
  • S + W + T = 72
Substituting S and T in terms of W:
  • (7/9)T + W + 2W - (7/9)T = 72
  • 3W = 72
  • W = 24
Therefore, Swetha can cut 24 apples in one hour.
So, the correct answer is option B: 24.

Ramu, Hari and Sanjay are three typists, who working simultaneously, can type 228 pages in four hours. In one hour, Sanjay can type as many pages more than Hari as Hari can type more than Ramu. During a period of five hours, Sanjay can type as many passages as Ramu can, during seven hours. How many pages does each of them type per hour?
  • a)
    16, 18, 22
  • b)
    14, 17, 20
  • c)
    15, 17, 22
  • d)
    15, 18, 21
  • e)
    16, 19, 22
Correct answer is option 'E'. Can you explain this answer?

Let Rohit, Harsh and Sanjeev can type x, y and z pages respectively in 1 h. Therefore, they together can type 4(x + y + z) pages in 4 h
∴ 4(x + y + z) = 228
⇒ x + y + z = 57 …..(i)
Also, z – y = y – x
i.e., 2y = x + z ……(ii)
5z = 7x ……(iii)
From Eqs. (i) and (ii), we get
3y = 57
⇒ y = 19
From Eq. (ii), x + z = 38
x = 16 and z = 22

When Ashok and Karthik are working alone, they can complete a piece of work in 25 days and 30 days respectively. On day 1, Karthik started the work and Ashok joined B from day 3 on-wards. Find approximately after how many days will the work be completed?
  • a)
    20 days
  • b)
    10 days
  • c)
    15 days
  • d)
    25 days
  • e)
    30 days
Correct answer is option 'C'. Can you explain this answer?

Aisha Gupta answered
Fraction of work completed by Karthik on day 1 and day 2 = 2* 1/30 = 1/15
Fraction of work left after 2 days = 14/15
Fraction of work completed by Both = 1/25 + 1/30 = 11/150
Number of days after day 2 to complete work = 14*150/15*11 = 13 days
So after 2+13 = 15 days works will be completed

Angel can do a piece of work in 10 days, Balu in 15 days. They work together for 5 days, the rest of the work is finished by Chitra in two more days. If they get Rs. 6000 as wages for the whole work, what are the daily wages of Angel, Bala and Chitra respectively?
  • a)
    200, 250, 300
  • b)
    300, 200, 250
  • c)
    600, 400, 200
  • d)
    600, 400, 500
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?

Angel’s 5 days work = 50%
Balu’s 5 days work = 33.33%
Chitra’s 2 days work = 16.66%
[100- (50+33.33)]
Ratio of work of Angel, Balu and Chitra = 3: 2: 1
Angel’s total share = Rs. 3000
Balu’s total share = Rs. 2000
Chitra’s total share = Rs. 1000
Angel’s one day’s wage = Rs.600
Balu’s one day’s wage = Rs.400
Chitra’s one day’s wage = Rs.500

Ravi can do a piece of work in 16 days. Rakesh can do the same work in 64/5 days, while Geeta can do it in 32 days. All of them started to work together but Ravi leaves after 4 days. Rakesh leaves the job 3 days before the completion of the work. How long would the work last?
  • a)
    6 days
  • b)
    9 days
  • c)
    18 days
  • d)
    5 days
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?

Kavya Saxena answered
Let the work lasted for x days,
Ravi’s 4 day’s work + Rakesh (x – 3) day’s work + Geeta’s x day’s work = 1
⇒ (4/16) + (x – 3) / (64/5) + x/32 = 1
⇒ 5(x – 3)/64 + x/32 = 1 – 1/4
⇒ [5(x – 3) + 2x] / 64 = 3/4
⇒ 7x – 15 = 48
∴ x = (48 + 15)/7 = 63/7 = 9 days

Madhavan can finish a work in 5 hours. He invites Manohar and Manjima who can work 3/4th as fast as he can to join him. He also invites Mani and Mohan who can work only 1/5th as fast as he can to join him. If the five person team works the same job and they start together, how long will it take for them to finish the job?
  • a)
    50/97 days
  • b)
    87 days
  • c)
    50/29 days
  • d)
    78 days
  • e)
    62 days
Correct answer is option 'C'. Can you explain this answer?

Anaya Patel answered
Let the work be 100 units.
Madhavan’s 1 hour work = 100/5 = 20 units
Manohar and Manjima’s 1 day work = 3/4 × 20 = 15 units.
Mohan and Mani’s 1 day work = 1/5 × 20 = 4 units.
In one day all five of them can do = 20 + 15 + 15 + 4 + 4 = 58 units of work. Hence they can complete the work in 100/58 days.

X can do a piece of work in 20 days. He worked at it for 5 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?
  • a)
    12 days
  • b)
    15 days
  • c)
    10 days
  • d)
    5 days
Correct answer is option 'C'. Can you explain this answer?

Rahul Mehta answered
  • X’s five day work = 5/20 = 1/4. Remaining work = 1 – 1/4 = 3/4.
  • This work was done by Y in 15 days. Y does 3/4th of the work in 15 days, he will finish the work in 15 × 4/3 = 20 days.  
  • X & Y together would take 1/20 + 1/20 = 2/20 = 1/10 i.e. 10 days to complete the work.

A building contractor undertook to finish a certain work in 162 days and employed 150 men. After 72 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work finish in time?
  • a)
    80
  • b)
    75
  • c)
    90
  • d)
    70
  • e)
    65
Correct answer is option 'C'. Can you explain this answer?

Rajeev Kumar answered
M1 = 150, M2 = 150 – n, D1 = 72, D2 = 90
W1= 2/3 and W2 = 1/3
According to the formula,
(M1D1) / W1 = (M2D2) / W2
⇒ [150 x 72] / 2 = [(150 – n) x 90] / 1
⇒ (150 x 72) / (2 x 60) = (150 – n)
⇒ (150 – n) = 60
∴ n = 150 – 60 = 90

Gopal does a work in 90 days, Vikash in 40 days and Santhosh in 12 days. They work one after another for a day each, starting with Gopal followed by Vikash and then by Santhosh. If the total wages received are Rs 360 and Gopal, Vikash, Santhosh share them in the ratio of the work done, find their respective individual wages.
  • a)
    Rs 44, Rs 80 and Rs 264
  • b)
    Rs 40, Rs 87 and Rs 276
  • c)
    Rs 36, Rs 81 and Rs 243
  • d)
    Rs 42, Rs 86 and Rs 232
  • e)
    Rs 37, Rs 89 and Rs 284
Correct answer is option 'C'. Can you explain this answer?

Rajeev Kumar answered
Assume there are 360 units of work (LCM of 90, 40 and 12).
Hence, they can do 4,9 and 30 units per day or together 43 units every 3 days.
So In 24 days, 43×8=344 units of work is completed.
In the next 2 days, 13 unitsare completed and on 27th day,Santhosh takes 1/10 thof a day to finish the rest.
So, gopal and vikash worked for 9 days each and have hence put in 36 and 81 units respectively, and the rest of the 243 units is put in by santhosh.
The wages shall also be distributed in the same ratio as: Rs 36, Rs 81 and Rs 243.

A, B and C together can complete a work in 8 days. If A is 50% more efficient than B and B is 50% less efficient than C, then B alone will complete the same work in:
  • a)
    16 days
  • b)
    24 days
  • c)
    48 days
  • d)
    36 days
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?

Mihir Chawla answered
Solution:

Let's assume that C can complete the work in x days.

Efficiency of B compared to C:
B is 50% less efficient than C. This means B can complete only half the work that C can complete in the same time. So, B can complete the work in 2x days.

Efficiency of A compared to B:
A is 50% more efficient than B. This means A can complete 1.5 times the work that B can complete in the same time. So, A can complete the work in (2x/1.5) days.

Efficiency of A, B, and C together:
Given that A, B, and C together can complete the work in 8 days. So, their combined efficiency is 1/8 of the work per day.

Let's calculate their combined efficiency:
1/A + 1/B + 1/C = 1/8

Substituting the values of A, B, and C:
1/(2x/1.5) + 1/2x + 1/x = 1/8

Taking the LCM and simplifying the equation:
[(1.5 + 3 + 4)/2x] = 1/8
8/2x = 1/8
2x = 64
x = 32

So, C alone can complete the work in 32 days.

Now, let's find out how many days B alone will take to complete the work:
B can complete the work in 2x days.
Substituting the value of x:
B can complete the work in 2(32) = 64 days.

Therefore, the correct answer is option D) 36 days.

A can do a piece of work in 40 days B can do the same piece of work in 60 days. A and B started the work together in the first 15 days A worked with 50% of his efficiency, in the next 15days B worked with 50% of his efficiency. Now in how many days does the remaining work will be completed if both of them work with their full efficiencies?
  • a)
    1 Day
  • b)
    1.5 Days
  • c)
    2 Days
  • d)
    2.5 Days
  • e)
    None
Correct answer is option 'B'. Can you explain this answer?

Aarav Sharma answered
Given:
A can do the work in 40 days
B can do the work in 60 days
In the first 15 days, A worked with 50% of his efficiency
In the next 15 days, B worked with 50% of his efficiency

To find:
In how many days will the remaining work be completed if both of them work with their full efficiencies?

Solution:
Let the total work be 120 units (LCM of 40 and 60)
A's 1-day work = 3 units (120/40)
B's 1-day work = 2 units (120/60)

In the first 15 days,
A's work = (15 days) × (1/2) × (3 units/day) = 22.5 units
Remaining work = 120 units - 22.5 units = 97.5 units

In the next 15 days,
B's work = (15 days) × (1/2) × (2 units/day) = 15 units
Total work done in 30 days = 22.5 units + 15 units = 37.5 units
Remaining work = 120 units - 37.5 units = 82.5 units

Let the number of days required to complete the remaining work be x.
A and B work together for x days to complete the remaining work.
∴ A's work in x days + B's work in x days = 82.5 units
⇒ x × (3 units/day) × (100/100) + x × (2 units/day) × (100/100) = 82.5 units
⇒ 5x = 82.5
⇒ x = 16.5 days

Therefore, the remaining work will be completed in 16.5 days.
But we need to find the total number of days taken to complete the entire work.
Total number of days = 15 days + 15 days + 16.5 days = 46.5 days

Hence, the correct option is (b) 1.5 Days.

Kiran can do a work in 25 days, while Ravi can do the same work in 50 days. They started the work jointly. Few days later Sumit also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs.600. What is the Share of Sumit?
  • a)
    Rs.360
  • b)
    Rs.385
  • c)
    Rs.240
  • d)
    can’t be determined
  • e)
    None of these
Correct answer is option 'C'. Can you explain this answer?

Aarav Sharma answered
Not be determined

Kiran's one day work=1/25
Ravi's one day work=1/50
Let Sumit's one day work=x
Together their one day work=(1/25)+(1/50)+x=3/50+x
In 10 days, their total work=10*(3/50+x)=3/5+10x
As they completed the whole work, we can equate it to 1.
3/5+10x=1
10x=2/5
x=1/25
So, Sumit's one day work=1/25
Therefore, his share= (1/25)*(10 days)*(Rs.600 total payment)=Rs.240
Hence, the answer is (c) Rs.240.

Two pipes, when working one at a time, can fill a cistern in 3 hours and 4 hours, respectively while a third pipe can drain the cistern empty in 8 hours. All the three pipes were opened together when the cistern was 1/12 full. How long did it take for the cistern to be completely full?
  • a)
    2 hours
  • b)
    1 hour 45 minutes
  • c)
    2 hour 11 minutes
  • d)
    2 hour 10 minutes
Correct answer is option 'A'. Can you explain this answer?

EduRev CLAT answered
Let the total amount of work in filling a cistern be 24 units. (LCM of 3, 4 and 8)
Work done by pipe 1 in 1 hour = 24/3 = 8 units.
Work done by pipe 2 in 1 hour = 24/4 = 6 units.
Work done by pipe 3 in 1 hour = 24/ (-8) = -3 units
Total work done in 1 hour = 8 + 6 – 3 = 11 units
The time required to complete 11/12th of the work = 11/12 × 24/ 11 = 2 hours
∴ The correct answer is 2 hours.

Chitra is twice efficient as Arun. Bala takes thrice as many days as Chitra. Arun takes 12 days to finish the work alone. If they work in pairs(i.e Arun-Bala, BalaChitra, Chitra-Arun) starting with Arun – Bala on the first day, Bala – Chitra on the second day and Chitra – Arun on the third day and so on, then how many days are required to finish the work?
  • a)
    26/9 days
  • b)
    46/9 days
  • c)
    16/9 days
  • d)
    56/9 days
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?

Faizan Khan answered
No of days taken by Arun = 12 days
No of days(Arun:Bala:Chitra) = 2:3:1
1 day work of (Arun+Bala) = 5/36
1 day work of (Bala+Chitra) = 8/36
1 day work of (Chitra+Arun) = 9/36
5 days total work – 35/36
1/36 is done by Arun-Chitra
Number of days taken by Arun-Chitra for the rest of the work = (1/36)/(9/36) = 1/9
Total time taken to complete the work = 5 + 1/9 = 46/9 days

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?
  • a)
    60
  • b)
    45
  • c)
    40
  • d)
    30
Correct answer is option 'A'. Can you explain this answer?

Rahul Mehta answered
1st method:
A and B complete a work in = 15 days
One day's work of (A + B) = 1/ 15
B complete the work in = 20 days;
One day's work of B = 1/20
Then, A's one day's work
=1/15−1/20
=(4−3)/6
=1/60
Thus, A can complete the work in = 60 days.

Two sprinters run the same race of100 m One runs at a speed of 10 m/s and the other runs at 8 m/s. By what time will the first sprinter beat the other sprinter?
  • a)
    1.5 sec
  • b)
    2 sec
  • c)
    2.5sec
  • d)
    3 sec
Correct answer is option 'C'. Can you explain this answer?

Navya Chavan answered
To determine the time it takes for the first sprinter to beat the second sprinter, we need to compare their speeds and calculate the time it takes for the first sprinter to cover a distance of 100m.

Let's start by calculating the time it takes for each sprinter to cover 100m:

- Sprinter 1 runs at a speed of 10m/s, so the time it takes for Sprinter 1 to cover 100m is:
Time = Distance / Speed = 100m / 10m/s = 10 seconds

- Sprinter 2 runs at a speed of 8m/s, so the time it takes for Sprinter 2 to cover 100m is:
Time = Distance / Speed = 100m / 8m/s = 12.5 seconds

From the above calculations, we can see that Sprinter 1 takes 10 seconds to cover 100m, while Sprinter 2 takes 12.5 seconds to cover the same distance.

Now, let's find out the time difference between the two sprinters:

- Time difference = Time taken by Sprinter 2 - Time taken by Sprinter 1
Time difference = 12.5 seconds - 10 seconds = 2.5 seconds

Therefore, the first sprinter beats the second sprinter by a time difference of 2.5 seconds. Hence, the correct answer is option 'C' - 2.5 seconds.

Dinesh does 80% of a work in 20 days. He then calls in Gokul and theytogether finish the remaining work in 3 days. How long Gokul alone would take to do the whole work?
  • a)
    39 days
  • b)
    37 days
  • c)
    37 ½ days
  • d)
    40 days
  • e)
    39 ½ days
Correct answer is option 'C'. Can you explain this answer?

Rajeev Kumar answered
Dinesh work done = 20*5/4 = 25 days
1/5 workdone by Dinesh and gokul in 3days.
Whole work done = 15 days
Dinesh 1 days work = 1/25
Dinesh and gokul’s 1 day work = 1/15
Gokul’s 1 day work = 1/15 – 1/25 = 2/75
Gokul alone in 75/2 days or 37 ½ days.

A can do a piece of work in 30 days, B can do in 45 days and C can do same work alone in 60 days. If on the first day A worked alone and on the second day A and B worked together and on the third day A and C worked together. If they repeat the cycle as follows then in how many days total work can be completed?
  • a)
    21 Days
  • b)
    21 7/8 Days
  • c)
    21 5/6 Days
  • d)
    21 4/9 Days
  • e)
    None
Correct answer is option 'C'. Can you explain this answer?

Aarav Sharma answered
Given: A can do a piece of work in 30 days, B can do in 45 days and C can do the same work alone in 60 days.

Let the total work be 180 units (LCM of 30, 45 and 60).

On the first day, A alone does 6 units of work (180/30).

On the second day, A and B together do (6+4) 10 units of work (LCM of 30 and 45 is 90, and A does 3 units of work in 1 day while B does 2 units of work in 1 day. So, in 1 day they will do 5 units of work. So, in 2 days, they will do 10 units of work).

On the third day, A and C together do (6+3) 9 units of work (LCM of 30 and 60 is 60, and A does 1 unit of work in 1 day while C does 1/3 units of work in 1 day. So, in 1 day they will do 4/3 units of work. So, in 3 days, they will do 4 units of work).

So, in 3 days, they have done a total of 25 units of work (6+10+9).

To complete 180 units of work, they need 155 units more (180-25).

Let's calculate the next 3 days cycle:

On the fourth day, A alone does 6 units of work.

On the fifth day, A and B together do 10 units of work.

On the sixth day, A and C together do 9 units of work.

So, in 6 days, they have done a total of 50 units of work (25+6+10+9).

To complete 180 units of work, they need 130 units more (180-50).

Let's calculate the next 3 days cycle:

On the seventh day, A alone does 6 units of work.

On the eighth day, A and B together do 10 units of work.

On the ninth day, A and C together do 9 units of work.

So, in 9 days, they have done a total of 75 units of work (25+6+10+9+6+10+9).

To complete 180 units of work, they need 105 units more (180-75).

Let's calculate the next 3 days cycle:

On the tenth day, A alone does 6 units of work.

On the eleventh day, A and B together do 10 units of work.

On the twelfth day, A and C together do 9 units of work.

So, in 12 days, they have done a total of 100 units of work (25+6+10+9+6+10+9+6+10+9).

To complete 180 units of work, they need 80 units more (180-100).

Let's calculate the next 3 days cycle:

On the thirteenth day, A alone does 6 units of work.

On the fourteenth day, A and B together do 10 units of work.

On the fifteenth day, A and C together do 9 units of work.

So, in 15 days, they have done a total of 125

Chapter doubts & questions for Time and Work - Mathematics for RRB NTPC / ASM 2025 is part of RRB NTPC/ASM/CA/TA exam preparation. The chapters have been prepared according to the RRB NTPC/ASM/CA/TA exam syllabus. The Chapter doubts & questions, notes, tests & MCQs are made for RRB NTPC/ASM/CA/TA 2025 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests here.

Chapter doubts & questions of Time and Work - Mathematics for RRB NTPC / ASM in English & Hindi are available as part of RRB NTPC/ASM/CA/TA exam. Download more important topics, notes, lectures and mock test series for RRB NTPC/ASM/CA/TA Exam by signing up for free.

Signup to see your scores go up within 7 days!

Study with 1000+ FREE Docs, Videos & Tests
10M+ students study on EduRev