In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)
    Correct answer is between '7.5,7.55'. Can you explain this answer?
    Verified Answer
    In a hydroelectric plant, the available head is 80 m for a discharge 1...
    P = WQHη KW
    = 9.81 × 12 × 80 × 0.8
    = 7534.08 KW = 7.53 MW
    View all questions of this test
    Most Upvoted Answer
    In a hydroelectric plant, the available head is 80 m for a discharge 1...
    The formula for power developed in a hydroelectric plant is:

    P = Qρghη

    where:
    P = power developed (in watts)
    Q = discharge (in cubic meters per second)
    ρ = specific weight of water (in newtons per cubic meter)
    g = acceleration due to gravity (9.81 m/s^2)
    h = available head (in meters)
    η = overall efficiency of the PowerStation (as a decimal)

    Plugging in the given values, we get:

    P = (12)(9.81)(80)(0.80)
    P = 75,878.4 watts

    Therefore, the power developed is approximately 75,878.4 watts.
    Explore Courses for Electrical Engineering (EE) exam

    Top Courses for Electrical Engineering (EE)

    In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer?
    Question Description
    In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer?.
    Solutions for In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
    Here you can find the meaning of In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer?, a detailed solution for In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer? has been provided alongside types of In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In a hydroelectric plant, the available head is 80 m for a discharge 12m3/sec, and overall efficiency of the PowerStation of 80%. The specific weight of water is 9.81 k/m2. Then the power developed is – (in MW)Correct answer is between '7.5,7.55'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
    Explore Courses for Electrical Engineering (EE) exam

    Top Courses for Electrical Engineering (EE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev