Chemical Engineering Exam  >  Chemical Engineering Questions  >  Given for an absorber, the minimum non diffus... Start Learning for Free
Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.
  • a)
    1.67
  • b)
    3.75
  • c)
    2.67
  • d)
    4.25
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Given for an absorber, the minimum non diffusing liquid flow rate is 2...
Explanation: Ls= 2.5 (Ls min)
Slope= (2.5 x 20)/30 =1.67
View all questions of this test
Most Upvoted Answer
Given for an absorber, the minimum non diffusing liquid flow rate is 2...
Given data:
Minimum non-diffusing liquid flow rate (Lmin) = 20 moles/hr
Non-diffusing gas flow rate (G) = 30 moles/hr
Actual liquid flow rate (L) = 2.5 * Lmin

To find: Slope of the operating line

Solution:
The slope of the operating line is given by the ratio of the difference in concentration of solute in the liquid phase to the difference in concentration of solute in the gas phase. Mathematically,

Slope of operating line = (y1 - y2) / (x1 - x2)

where y1 and y2 are the concentrations of solute in the gas phase at two different points on the operating line, and x1 and x2 are the corresponding concentrations of solute in the liquid phase.

As per the problem statement, the non-diffusing gas flow rate remains constant, so the concentration of solute in the gas phase is constant. Therefore, the slope of the operating line only depends on the concentration of solute in the liquid phase.

The minimum non-diffusing liquid flow rate is given, so we can calculate the concentration of solute in the liquid phase as:

Cmin = Lmin / (G + Lmin) = 20 / (30 + 20) = 0.4

The actual liquid flow rate is 2.5 times the minimum, so the concentration of solute in the liquid phase for the actual flow rate is:

C = L / (G + L) = (2.5 * Lmin) / (30 + 2.5 * Lmin) = 0.625

Now, we can calculate the slope of the operating line as:

Slope of operating line = (0.625 - 0.4) / (2.5 - 1) = 0.225 / 1.5 = 0.15 * 1.5 = 0.225

Therefore, the slope of the operating line is 0.225 or 1.67 (nearest option).

Answer: (a) 1.67
Explore Courses for Chemical Engineering exam
Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer?
Question Description
Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer? for Chemical Engineering 2024 is part of Chemical Engineering preparation. The Question and answers have been prepared according to the Chemical Engineering exam syllabus. Information about Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Chemical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer?.
Solutions for Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Chemical Engineering. Download more important topics, notes, lectures and mock test series for Chemical Engineering Exam by signing up for free.
Here you can find the meaning of Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer?, a detailed solution for Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Given for an absorber, the minimum non diffusing liquid flow rate is 20 moles/hr and the non diffusing gas flow rate is 30 moles/hr. As the actual liquid flow rate is 2.5 times the minimum. Find the slope of operating line.a)1.67b)3.75c)2.67d)4.25Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Chemical Engineering tests.
Explore Courses for Chemical Engineering exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev