Question Description
A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realized that the work would delayed by three-fourth of the scheduled time. So, he at once doubled the number of workers and thus he managed to finish the road on the scheduled time. How much work had been completed before increasing the number of workers?a)b)c)20%d)None of the aboveCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.