Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved. 

Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.
  • a)
    Crew Alpha: 10 hr
    Crew Zeta: 20 hr
  • b)
    Crew Alpha: 60 hr
    Crew Zeta: 30 hr
  • c)
    Crew Alpha: 40 hr
    Crew Zeta: 10 hr
  • d)
    Crew Alpha: 20 hr
    Crew Zeta: 60 hr
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Work crews Alpha and Zeta are repaving a section of freeway in Los Ang...
To solve this problem, you must create a model that generates the potential solutions. The total distance paved by Crew Alpha is 12*A, and the total distance paved by Crew Zeta is 10*Z, where A and Z are the hours worked by the respective crews. Thus, the answer will be a solution to: 

12A + 10Z = Distance To Be Paved 

Note that 480 meters of highway have already been paved (12 meters/hour * 40 hours), so there are only 1020 meters remaining. This gives you: 

12A + 10Z = 1020 

By plugging in values from one column, you will be able to compare the result with values from the second column, and you will find that A = 60, Z = 30 gives you the correct answer. 

12(60) + 10Z = 1020
10Z = 300
Z = 30
View all questions of this test
Most Upvoted Answer
Work crews Alpha and Zeta are repaving a section of freeway in Los Ang...
To solve this problem, we need to determine the number of hours each crew will work in order to complete the project. Let's break it down step by step:

1. Convert the length of the freeway section to meters:
- 1.5 kilometers = 1,500 meters

2. Determine the rate at which each crew is working:
- Work crew Alpha is paving at a rate of 12 meters per hour.
- Work crew Zeta is paving at a rate of 10 meters per hour.

3. Calculate the total number of working hours for each crew:
- Work crew Alpha started one week (40 working hours) earlier than work crew Zeta. So, the total working hours for crew Alpha will be 40 hours plus the additional hours needed to complete the project.
- Work crew Zeta will work the additional hours needed to complete the project.

4. Determine the distance each crew needs to cover:
- Work crew Alpha started at the north end of the freeway and has already paved a certain distance. Let's denote this distance as "d1".
- Work crew Zeta started at the south end of the freeway and needs to pave the remaining distance. Let's denote this distance as "d2".

5. Set up an equation to solve for the number of hours each crew will work:
- The equation is: (d1 + d2) / 12 = (d2) / 10 + 40
- The left side of the equation represents the time it takes for crew Alpha to complete their work (d1 + d2) divided by their rate of 12 meters per hour.
- The right side of the equation represents the time it takes for crew Zeta to complete their work (d2) divided by their rate of 10 meters per hour, plus the 40 additional hours they started later.

6. Solve the equation for the number of hours:
- Simplifying the equation: 10(d1 + d2) = 12(d2) + 480
- Distributing: 10d1 + 10d2 = 12d2 + 480
- Combining like terms: 10d1 - 12d2 = 480
- Rearranging the equation: 2d2 = 10d1 - 480
- Dividing by 2: d2 = 5d1 - 240

7. Substitute the value of d2 back into the equation to solve for d1:
- Substituting: 5d1 - 240 = d2
- Rewriting as: 5d1 - 240 = 5d1 - 240
- The equation is satisfied regardless of the value of d1.

8. Determine the number of hours each crew will work:
- Since d1 and d2 can be any value, we can choose a value that makes the calculation easier. Let's choose d1 = 240 meters, which means d2 = 0 meters.
- Plugging this into the equation: (240 + 0) / 12 = (0) / 10 + 40
- Simplifying: 240 / 12 = 0 + 40
- Solving: 20 = 40
- This equation is not true, so we need to choose a
Attention GMAT Students!
To make sure you are not studying endlessly, EduRev has designed GMAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in GMAT.
Explore Courses for GMAT exam

Similar GMAT Doubts

Article 1From a local Southern California newspaper.Typically, fewer people vote in local elections that in national ones, but participation can vary widely by state. A new poll has found that more people in California vote in local elections than do people in Nevada, Arizona, and New Mexico combined. This has been attributed to the high number of independent voters in our state, as well as the high enthusiasm for local elections. City councilman Brad Zellman was pleased to see such a high turnout at the recent city council election. “It’s a unique opportunity for local citizens’ votes to carry more weight than they would in big national elections, and it’s great to have so much participation in these smaller campaigns state-wide.”Article 2Editorial from the Opinion section of a competing newspaper.The recent city council election has seen many a politico claim that the increased voter turnout is due to local citizens wanting to be a part of an election where their vote is proportionally more important. However, it is incorrect to suggest that voting in local elections somehow means your vote “counts more.” True, local politicians make decisions that affect day-to-day operations of our cities, but national politicians make decisions that ultimately affect the outcomes of our lives. When you vote for national figures in larger elections, your vote matters more because you are voting for people who will ultimately have a bigger impact on your life long-term.Article 3Results from recent California elections.City councilman elections: 13,000 local votes cast (22% of the eligible population vote d), 80% of citizens who voted were polled as “extremely satisfied” with the results. District representative elections: 1.9 million votes cast (19% of the eligible population voted), 67% of citizens who voted were polled as “extremely satisfied” with the results.Consider each of the following statements. Does the information in the articles support the inference as stated?Californians are more concerned with politics than are people in Nevada, Arizona, and New Mexico.The “weight” Zellman describes refers to the scale of political decision-making.

Top Courses for GMAT

Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer?
Question Description
Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer? for GMAT 2024 is part of GMAT preparation. The Question and answers have been prepared according to the GMAT exam syllabus. Information about Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for GMAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GMAT. Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Work crews Alpha and Zeta are repaving a section of freeway in Los Angeles. Work crew Alpha started its work one week (40 working hours) earlier than work crew Zeta, and started on the north end of the freeway, working its way south at a rate of 12 meters per hour since starting the job. Now, work crew Zeta has started at the south end, working its way north at a rate of 10 meters per hour. The section of freeway that needs to be repaved is 1.5 kilometers long, including the section that has already been paved.Given that each crew will not necessarily work the same number of hours, which of the following answer choices represents an hourly workload for each crew that will finish the project? Please make only one selection in each column.a)Crew Alpha: 10 hrCrew Zeta: 20 hrb)Crew Alpha: 60 hrCrew Zeta: 30 hrc)Crew Alpha: 40 hrCrew Zeta: 10 hrd)Crew Alpha: 20 hrCrew Zeta: 60 hrCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice GMAT tests.
Explore Courses for GMAT exam

Top Courses for GMAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev