A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer? for UPSC 2024 is part of UPSC preparation. The Question and answers have been prepared
according to
the UPSC exam syllabus. Information about A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for UPSC 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer?.
Solutions for A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for UPSC.
Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free.
Here you can find the meaning of A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer?, a detailed solution for A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left. Then, B and C together completed the work in 10 more days. A alone could complete the work in workinga) 15 days b) 16 days c) 25 days d) 50 days Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice UPSC tests.