For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.
  • a)
    0.200 m3
  • b)
    0.217 m3
  • c)
    0.340 m3
  • d)
    None of these
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, th...
Plastering thickness 12 mmc= 12/1000 = 0.012m
Volume of cement mortar required = (Plastering Area x thickness) = 100 m2 x 0.012m = 1.2 m3
(This is wet volume that means we need this much volume of cement mortar after mixing water, So for dry volume, we have to add 30-35% as bulkage of sand, we are using 35% and wastage as 20%)
Consider 35% Sand Bulkage = 1.2 m3 x (1 + 0.2 + 0.35) = 1.86 m3
Cement required = (1/7) x 1.86 = 0.265 m3
View all questions of this test
Most Upvoted Answer
For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, th...
Given:
Thickness of cement plastering = 12 mm
Ratio of cement mortar = 1:6
Area of plastering = 100 sq. m

To find: Quantity of cement required

Calculation:
1. Volume of cement mortar required for 100 sq. m plastering:
Volume of plastering = Area x Thickness
= 100 x 0.012
= 1.2 cubic meter

Volume of cement mortar required = 1.2/(1+6) = 0.1714 cubic meter

2. Quantity of cement required:
Quantity of cement = (1/7) x 0.1714 = 0.0245 cubic meter

Therefore, the quantity of cement required for 12 mm thick cement plastering 1:6 on 100 sq. m new brickwork is none of these. It is not possible to determine the quantity of cement required without knowing the density of cement.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer?
Question Description
For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer?.
Solutions for For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For 12 mm thick cement plastering 1:6 on 100 sq. m, new brick work, the quantity of cement required is _____.a)0.200 m3b)0.217 m3c)0.340 m3d)None of theseCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev