.Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).?
Most Upvoted Answer
.Calculate the quantity of the sand required for 8 cubic meter brick w...
To calculate the quantity of sand required for 8 cubic meter brickwork with cement mortar (1:3), we need to follow the below steps:

Step 1: Find the volume of brickwork

The volume of brickwork is given as 8 cubic meter.

Step 2: Find the proportion of cement mortar

The proportion of cement mortar is given as 1:3 i.e. 1 part of cement and 3 parts of sand.

Step 3: Find the volume of cement mortar

To find the volume of cement mortar, we need to first calculate the total proportion of the mixture.

Total proportion = 1+3 = 4

Now, we can calculate the volume of cement mortar as:

Volume of cement mortar = (1/4) x volume of brickwork

Volume of cement mortar = (1/4) x 8

Volume of cement mortar = 2 cubic meter

Step 4: Find the quantity of sand required

As per the proportion of cement mortar, the quantity of sand required will be three times the quantity of cement.

Quantity of sand required = 3 x quantity of cement

As we know the volume of cement mortar is 2 cubic meter, we can calculate the quantity of cement as:

Quantity of cement = (1/4) x volume of brickwork

Quantity of cement = (1/4) x 8

Quantity of cement = 2 cubic meter

Now, we can calculate the quantity of sand required as:

Quantity of sand required = 3 x 2

Quantity of sand required = 6 cubic meter

Therefore, the quantity of sand required for 8 cubic meter brickwork with cement mortar (1:3) is 6 cubic meter.
Community Answer
.Calculate the quantity of the sand required for 8 cubic meter brick w...
1.8
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

.Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).?
Question Description
.Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).?.
Solutions for .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).? defined & explained in the simplest way possible. Besides giving the explanation of .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).?, a detailed solution for .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).? has been provided alongside types of .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).? theory, EduRev gives you an ample number of questions to practice .Calculate the quantity of the sand required for 8 cubic meter brick work with cement mortar (1:3).? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev