.Calculate the quantity of the sand required for 8 cubic meter brick w...
To calculate the quantity of sand required for 8 cubic meter brickwork with cement mortar (1:3), we need to follow the below steps:
Step 1: Find the volume of brickwork
The volume of brickwork is given as 8 cubic meter.
Step 2: Find the proportion of cement mortar
The proportion of cement mortar is given as 1:3 i.e. 1 part of cement and 3 parts of sand.
Step 3: Find the volume of cement mortar
To find the volume of cement mortar, we need to first calculate the total proportion of the mixture.
Total proportion = 1+3 = 4
Now, we can calculate the volume of cement mortar as:
Volume of cement mortar = (1/4) x volume of brickwork
Volume of cement mortar = (1/4) x 8
Volume of cement mortar = 2 cubic meter
Step 4: Find the quantity of sand required
As per the proportion of cement mortar, the quantity of sand required will be three times the quantity of cement.
Quantity of sand required = 3 x quantity of cement
As we know the volume of cement mortar is 2 cubic meter, we can calculate the quantity of cement as:
Quantity of cement = (1/4) x volume of brickwork
Quantity of cement = (1/4) x 8
Quantity of cement = 2 cubic meter
Now, we can calculate the quantity of sand required as:
Quantity of sand required = 3 x 2
Quantity of sand required = 6 cubic meter
Therefore, the quantity of sand required for 8 cubic meter brickwork with cement mortar (1:3) is 6 cubic meter.
.Calculate the quantity of the sand required for 8 cubic meter brick w...
1.8