A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is: 
  • a)
    2 minutes
  • b)
    2.4 minutes    
  • c)
    2.64 minutes  
  • d)
    2.67 minutes 
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
A stop watch time study on an operator with a performance rating of 12...
Standard time of the operation = Basic time + Allowances 

Standard time of the operation = 2.4 + 0.24 = 2.64 minutes. 
View all questions of this test
Most Upvoted Answer
A stop watch time study on an operator with a performance rating of 12...
Explanation:
To find the standard time of the operation, we need to consider the performance rating and the allowances given.

Given:
Performance rating = 120
Time measured = 2 minutes
Allowances = 10% of the total available time

Step 1: Calculate the total available time
To calculate the total available time, we divide the measured time by the performance rating:

Total available time = Time measured / Performance rating
= 2 minutes / 120
= 0.0167 minutes

Step 2: Calculate the allowances
To calculate the allowances, we multiply the total available time by the percentage allowances:

Allowances = Total available time * Percentage allowances
= 0.0167 minutes * 10%
= 0.00167 minutes

Step 3: Calculate the standard time
To calculate the standard time, we add the total available time and the allowances:

Standard time = Total available time + Allowances
= 0.0167 minutes + 0.00167 minutes
= 0.01837 minutes

Step 4: Convert the standard time to minutes
To convert the standard time to minutes, we round the value to two decimal places:

Standard time = 0.01837 minutes (rounded to 2 decimal places)
= 0.02 minutes
= 2.64 minutes

Therefore, the standard time of the operation is 2.64 minutes, which corresponds to option C.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer?
Question Description
A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:a)2 minutesb)2.4 minutes c)2.64 minutes d)2.67 minutesCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev