If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer? for CLAT 2024 is part of CLAT preparation. The Question and answers have been prepared
according to
the CLAT exam syllabus. Information about If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for CLAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer?.
Solutions for If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CLAT.
Download more important topics, notes, lectures and mock test series for CLAT Exam by signing up for free.
Here you can find the meaning of If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer?, a detailed solution for If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice If 20 people can complete 2/5th of a work in 6 days working 4 hours each day, then how much work will be completed by 30 people in 2 days working 8 hours each day?a)1b)4/5c)3/5d)2/5Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice CLAT tests.