Principle: Master is liable for the acts of his servant done in the course of his duties.
Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.
  • a)
    X is liable for the entire amount
  • b)
    X is liable for the part amount only i.e. for payment of the cost of half of the material
  • c)
    X is not liable for the misconduct/embezzlement of his employee
  • d)
    Z can claim the balance payment only from Y
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Principle: Master is liable for the acts of his servant done in the co...
As Y is the employee of X and he have done this in due course of employment which makes X liable for the entire amount. So, the correct option is (a).
View all questions of this test
Explore Courses for CLAT exam

Similar CLAT Doubts

Top Courses for CLAT

Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer?
Question Description
Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer? for CLAT 2025 is part of CLAT preparation. The Question and answers have been prepared according to the CLAT exam syllabus. Information about Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for CLAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CLAT. Download more important topics, notes, lectures and mock test series for CLAT Exam by signing up for free.
Here you can find the meaning of Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Principle: Master is liable for the acts of his servant done in the course of his duties.Facts: X hired an employee Y in his construction business. Y was the property in-charge who received construction material and gave receipts for the material received by him. Z claimed payment for cement supplied to X which was duly received by Y. X denied the payment on the ground that he has only received half of the material and the balance was misutilized by the employee Y.a)X is liable for the entire amountb)X is liable for the part amount only i.e. for payment of the cost of half of the materialc)X is not liable for the misconduct/embezzlement of his employeed)Z can claim the balance payment only from YCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice CLAT tests.
Explore Courses for CLAT exam

Top Courses for CLAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev