Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  A concrete beam is pre-stressed by a cable ca... Start Learning for Free
A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioning
Assume
Age of concrete at transfer = 8 days
  • a)
    0.67
  • b)
    1.5
  • c)
    2
  • d)
    2.5
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A concrete beam is pre-stressed by a cable carrying an initial pre-str...
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer?
Question Description
A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer?.
Solutions for A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A concrete beam is pre-stressed by a cable carrying an initial pre-stressing force of 300kN. The cross – sectional area of the wires in the cable is 300 mm2. Calculate the ratio of percentage loss of stress in cable only due to shrinkage of concrete due to pre-tensioning and post – tensioningAssumeAge of concrete at transfer = 8 days a)0.67b)1.5c)2d)2.5Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev