A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station is
  • a)
    1
  • b)
    0.75
  • c)
    0.67
  • d)
    0.5
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
A thermal generating station has an installed capacity of 15 MW and su...
View all questions of this test
Most Upvoted Answer
A thermal generating station has an installed capacity of 15 MW and su...
Given information:
- Installed capacity of thermal generating station = 15 MW
- Daily load:
- 10 MW for 12 hours
- 5 MW for the remaining 12 hours

To find: Plant capacity factor

Calculation:

Step 1: Find the energy supplied by the plant in a day

Energy supplied = Power x Time

For the first 12 hours, power supplied = 10 MW

Energy supplied in the first 12 hours = 10 MW x 12 hours = 120 MWh

For the remaining 12 hours, power supplied = 5 MW

Energy supplied in the remaining 12 hours = 5 MW x 12 hours = 60 MWh

Total energy supplied in a day = 120 MWh + 60 MWh = 180 MWh

Step 2: Find the maximum possible energy that could have been supplied by the plant in a day

Maximum possible energy = Installed capacity x 24 hours

Maximum possible energy = 15 MW x 24 hours = 360 MWh

Step 3: Calculate the plant capacity factor

Plant capacity factor = Energy supplied / Maximum possible energy

Plant capacity factor = 180 MWh / 360 MWh = 0.5

Therefore, the plant capacity factor for this station is 0.5.

Explanation:
- Plant capacity factor is a measure of how efficiently a power plant is being used.
- It is the ratio of actual energy output to the maximum possible energy output over a period of time.
- In this case, the plant supplied 180 MWh of energy in a day, compared to its maximum possible output of 360 MWh.
- Therefore, the plant capacity factor is 0.5, which means that the plant is being used at 50% of its maximum efficiency.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer?
Question Description
A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer?.
Solutions for A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer?, a detailed solution for A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW of remaining 12 hours. The plant capacity factor for this station isa)1b)0.75c)0.67d)0.5Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev