Electrical Engineering (EE) Exam  >  Electrical Engineering (EE) Questions  >  A generating station has the following data:I... Start Learning for Free
A generating station has the following data:
Installed capacity = 420 MW; capacity factor = 60%
Annual load factor = 70%.
The minimum reserve capacity of the station is – (in MW)
    Correct answer is '60'. Can you explain this answer?
    Verified Answer
    A generating station has the following data:Installed capacity = 420 M...

    By above two equations,
    Maximum demad = Installed capacity x 

    Reserve capacity = Installed capacity − Maximum demand
    = 420 – 360 = 60 MW
    View all questions of this test
    Most Upvoted Answer
    A generating station has the following data:Installed capacity = 420 M...
    To calculate the minimum reserve capacity of the station, we first need to determine the average power generated by the station.

    Average power generated = Installed capacity * Capacity factor
    = 420 MW * 0.60
    = 252 MW

    Next, we need to calculate the maximum power demand that the station needs to meet.

    Maximum power demand = Average power generated / Load factor
    = 252 MW / 0.70
    = 360 MW

    Finally, we can calculate the minimum reserve capacity by subtracting the maximum power demand from the installed capacity.

    Minimum reserve capacity = Installed capacity - Maximum power demand
    = 420 MW - 360 MW
    = 60 MW

    Therefore, the minimum reserve capacity of the station is 60 MW.
    Explore Courses for Electrical Engineering (EE) exam

    Top Courses for Electrical Engineering (EE)

    A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer?
    Question Description
    A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer?.
    Solutions for A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
    Here you can find the meaning of A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer?, a detailed solution for A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer? has been provided alongside types of A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A generating station has the following data:Installed capacity = 420 MW; capacity factor = 60%Annual load factor = 70%.The minimum reserve capacity of the station is – (in MW)Correct answer is '60'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
    Explore Courses for Electrical Engineering (EE) exam

    Top Courses for Electrical Engineering (EE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev