The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
  • a)
    Total Float
  • b)
    Free Float
  • c)
    Interfering Float
  • d)
    Independent Float
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
The time by which a particular activity can be delayed without affecti...
Total float affects both preceding and succeeding activities.
Free float affects only succeeding activities.
View all questions of this test
Most Upvoted Answer
The time by which a particular activity can be delayed without affecti...
Independent Float

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Independent Float. It is also sometimes referred to as Total Float, but it is important to note that Total Float is a broader concept that includes both Free Float and Interfering Float.

Understanding Float

Float is an important concept in project management, particularly in the field of construction. It refers to the amount of time that an activity can be delayed without causing a delay to the overall project schedule. Float allows for flexibility in project scheduling by identifying activities that have some leeway in terms of their start and finish dates.

Different Types of Float

1. Total Float: Total Float is the maximum amount of time that an activity can be delayed without delaying the project completion date. It is calculated by subtracting the Early Start (ES) of an activity from the Late Start (LS) of the same activity. Total Float is shared by all dependent activities and is an indicator of the project's overall flexibility.

2. Free Float: Free Float is the amount of time that an activity can be delayed without delaying the early start of any of its successor activities. It represents the flexibility within the activity itself and is calculated by subtracting the Early Finish (EF) of an activity from the Early Start (ES) of its successor activity.

3. Interfering Float: Interfering Float is the amount of time that an activity can be delayed without delaying the late start of any of its predecessor activities. It represents the flexibility within the activity itself and is calculated by subtracting the Late Finish (LF) of its predecessor activity from the Late Start (LS) of the same activity.

4. Independent Float: Independent Float is the time by which a particular activity can be delayed without affecting the preceding and succeeding activities. It is calculated by subtracting the Late Finish (LF) of the predecessor activity from the Early Start (ES) of the succeeding activity. Independent Float is specific to a particular activity and does not impact the overall project schedule.

Conclusion

In summary, the time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as Independent Float. It is a specific type of float that allows for flexibility within an activity without impacting the overall project schedule. Understanding and managing float is crucial in project management to ensure effective scheduling and timely project completion.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer?
Question Description
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer?.
Solutions for The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known asa)Total Floatb)Free Floatc)Interfering Floatd)Independent FloatCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev