The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is called
  • a)
    Free float
  • b)
    Total float
  • c)
    Independent float
  • d)
    Interfering float
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
The time span by which the starting or finishing of an activity can be...
Total float- The total time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project. It is also the excess of the minimum available time over activity time.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer?
Question Description
The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The time span by which the starting or finishing of an activity can be delayed without delaying the completion of the project, is calleda)Free floatb)Total floatc)Independent floatd)Interfering floatCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev