For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:
List-I                        List-ll
A. Free                    1. 5
B. Total                    2. 9
C. Interfering           3. 13
D. Independent       4. 18
Codes: A, B, C, D
  • a)
    4, 3, 1, 2
  • b)
    3, 4, 1, 2
  • c)
    3, 4, 2, 1
  • d)
    4, 3, 2, 1
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
For an activity i-j, the early event times at i and j, respectively ar...
Given Information:

- Activity i-j
- Early event times at i and j, respectively are 5, 24, 9 and 29 (EST = 5, LST = 9, EFT = 24, LFT = 29)
- Activity duration is 6

To find:

- Match List-I (Float) with List-ll (Duration)

Solution:

Float: Float is the amount of time an activity can be delayed without delaying the project duration.

Duration: Duration is the time required to complete an activity.

We can determine the float of activity i-j as follows:

Total Float (TF) = LFT - EFT - duration
TF = 29 - 24 - 6
TF = -1

As the total float is negative, the activity is critical.

Now we can match the float categories with their respective durations as follows:

- Free Float: The amount of time an activity can be delayed without delaying the early start of its successor activity. In this case, there is no successor activity for i-j, so the free float is zero. Duration = 0.
- Total Float: The amount of time an activity can be delayed without delaying the project duration. In this case, we have already calculated the total float to be -1. Duration = 1.
- Interfering Float: The amount of time an activity can be delayed without delaying the late start of its successor activity. In this case, there is no successor activity for i-j, so the interfering float is zero. Duration = 0.
- Independent Float: The amount of time an activity can be delayed without delaying the early start of any other activity. In this case, there are no activities that are dependent on i-j, so the independent float is equal to the free float, which is zero. Duration = 0.

Therefore, the correct answer is option B, which is 3, 4, 1, 2.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer?
Question Description
For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer?.
Solutions for For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer?, a detailed solution for For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:List-I List-ll A. Free 1. 5B. Total 2. 9C. Interfering 3. 13D. Independent 4. 18Codes: A, B, C, Da)4, 3, 1, 2b)3, 4, 1, 2c)3, 4, 2, 1d)4, 3, 2, 1Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev