The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is:
  • a)
    1 week
  • b)
    3 weeks
  • c)
    8 weeks
  • d)
    13 weeks
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The earliest date and latest date of the events 3 and 10 are given in...
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer?
Question Description
The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The earliest date and latest date of the events 3 and 10 are given in the above figure. Activity C is connecting both the events and its duration is 12 weeks. The independent float of the activity is: a)1 weekb)3 weeksc)8 weeksd)13 weeksCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev