Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:
List-I
A. Earliest start time of its successor activity minus earliest finish time' of the activity in question minus the duration
B. Time available for an activity performance minus the duration of the activity
C. Excess of minimum available time over the required activity duration
D. Difference between total float and free float of an activity
List-II
1. Total
2. Free
3. Interfering
4. Independent
Codes: A, B, C, D 
  • a)
    1, 2, 3, 4
  • b)
    1, 2, 4, 3
  • c)
    2, 1, 3, 4
  • d)
    2, 1, 4, 3
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Match List-1 (Description of activity floats) with List-11 (Names of t...
Matching Floats with Descriptions:

A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the duration - Interfering Float

B. Time available for an activity performance minus the duration of the activity - Free Float

C. Excess of minimum available time over the required activity duration - Independent Float

D. Difference between total float and free float of an activity - Total Float

The correct match between List-1 and List-11 is:

D. Difference between total float and free float of an activity - Total Float

C. Excess of minimum available time over the required activity duration - Independent Float

B. Time available for an activity performance minus the duration of the activity - Free Float

A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the duration - Interfering Float

Explanation:

Total Float:

- The amount of time an activity can be delayed without delaying the project's completion date is called Total Float.
- It is calculated by subtracting the earliest start time of the activity from the latest start time of the activity.
- Total Float = LS - ES or LF - EF

Independent Float:

- Independent float is the maximum amount of time that an activity can be delayed without delaying the early start of any of its successor activities.
- Independent Float = ES of succeeding activity - EF of current activity - duration of current activity

Free Float:

- Free float is the maximum amount of time that an activity can be delayed without delaying the early start of its immediate successor.
- Free Float = ES of succeeding activity - EF of current activity

Interfering Float:

- Interfering Float is the amount of time an activity can be delayed without delaying the start time of a specific interfering successor activity.
- Interfering Float = ES of interfering activity - EF of current activity - duration of current activity

Hence, the correct match between List-1 and List-11 is D, C, B, A.
Free Test
Community Answer
Match List-1 (Description of activity floats) with List-11 (Names of t...
List-I and List-II represent different types of floats associated with activity floats. The correct match between List-I and List-II is given in option 'D'. Let's understand each type of float and its associated name:

1. Total Float: It is the amount of time that an activity can be delayed without delaying the project's finish date. It is calculated as follows:
Total Float = Latest Start Time - Earliest Start Time or Latest Finish Time - Earliest Finish Time

Name of the Float: Total

2. Free Float: It is the amount of time that an activity can be delayed without delaying the start time of its successor activity. It is calculated as follows:
Free Float = Earliest Start Time of Successor Activity - Earliest Finish Time - Activity Duration

Name of the Float: Free

3. Interfering Float: It is the difference between the total float and the free float of an activity. It represents the amount of time that an activity can be delayed without delaying the start time of its successor activity, but delaying the project's finish date. It is calculated as follows:
Interfering Float = Total Float - Free Float

Name of the Float: Interfering

4. Independent Float: It is the excess of minimum available time over the required activity duration. It represents the amount of time that an activity can be delayed without delaying the start time of any other activity or the project's finish date. It is calculated as follows:
Independent Float = Minimum Available Time - Activity Duration

Name of the Float: Independent

Therefore, the correct match between List-I and List-II is as follows:
A - 2 (Free)
B - 1 (Total)
C - 4 (Independent)
D - 3 (Interfering)
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer?
Question Description
Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer?.
Solutions for Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:List-I A. Earliest start time of its successor activity minus earliest finish time of the activity in question minus the durationB. Time available for an activity performance minus the duration of the activityC. Excess of minimum available time over the required activity durationD. Difference between total float and free float of an activityList-II 1. Total2. Free3. Interfering4. IndependentCodes: A, B, C, Da)1, 2, 3, 4b)1, 2, 4, 3c)2, 1, 3, 4d)2, 1, 4, 3Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev