Whenever an activity has zero total float, then
  • a)
    free float of the activity must be zero but independent float need not be zero
  • b)
    independent float need not be zero
  • c)
    free float and independent float both must be zero
  • d)
    free float and independent float both need not be zero
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Whenever an activity has zero total float, thena)free float of the act...
Explanation:

Zero total float in a project schedule means that the project is on a critical path, and any delay in the activities on the critical path will directly impact the project's completion date. In such cases, it is important to understand the concepts of free float and independent float.

Free Float:
Free float is the amount of time that an activity can be delayed without delaying the early start date of any successor activity. It is the total amount of time that an activity can be delayed without affecting the project's completion date.

Independent Float:
Independent float is the amount of time that an activity can be delayed without delaying the early start date of any other activity in the project. It is the total amount of time that an activity can be delayed without affecting the early start dates of any other activities.

Answer:
The correct answer is option 'C' - free float and independent float both must be zero when an activity has zero total float.

This is because when an activity has zero total float, it means that it is on the critical path and any delay in its completion will directly impact the project's completion date. In such cases, there is no room for any delay, and hence both free float and independent float must be zero.

If an activity had non-zero free float, it would mean that it could be delayed without affecting the project's completion date, which contradicts the fact that it is on the critical path. Similarly, if an activity had non-zero independent float, it would mean that it could be delayed without affecting the early start dates of other activities, which again contradicts the fact that it is on the critical path.

Therefore, when an activity has zero total float, both free float and independent float must be zero to ensure that the project stays on schedule and any delay in the critical activities is avoided.
Free Test
Community Answer
Whenever an activity has zero total float, thena)free float of the act...
Mode means highest number of observations or occurrence of data most of the time as data 17, occurs four times, i.e., highest time. So mode is 17.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer?
Question Description
Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Whenever an activity has zero total float, thena)free float of the activity must be zero but independent float need not be zerob)independent float need not be zeroc)free float and independent float both must be zerod)free float and independent float both need not be zeroCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev