A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve is
  • a)
    3.0 MW
  • b)
    3.75 MW
  • c)
    6.0 MW
  • d)
    7.5 MW
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A power plant has a maximum demand of 15 MW. The load factor is 50% an...
View all questions of this test
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer?
Question Description
A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? for Electrical Engineering (EE) 2025 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factor is 40%. The operating reserve isa)3.0 MWb)3.75 MWc)6.0 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev