Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  The coincident draft is given bya)maximum hou... Start Learning for Free
The coincident draft is given by
  • a)
    maximum hourly demand –fire demand
  • b)
    maximum daily demand + fire demand
  • c)
    maximum hourly demand
  • d)
    greater of (b) and (c) above
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
The coincident draft is given bya)maximum hourly demand fire demandb)m...
Explanation:

The coincident draft is a term used in the design of water supply systems for firefighting purposes. It refers to the maximum flow rate that is required to fight a fire, which is the sum of the maximum daily demand and the maximum hourly demand.

Maximum Daily Demand:

The maximum daily demand is the amount of water that is required by a building or structure on a daily basis. It is usually calculated based on the number of occupants, the type of activity, and the amount of water that is used for various purposes such as washing, cooking, and drinking.

Maximum Hourly Demand:

The maximum hourly demand is the amount of water that is required by a building or structure during the peak hour of water usage. This is usually calculated based on the number of occupants, the type of activity, and the amount of water that is used for various purposes such as washing, cooking, and drinking.

Greater of (b) and (c) above:

The coincident draft is calculated by taking the greater value of the maximum daily demand and the maximum hourly demand. This is because during a fire, the demand for water can be much higher than the normal daily or hourly demand, and the water supply system must be able to meet this demand.

Conclusion:

In conclusion, the coincident draft is the sum of the maximum daily demand and the maximum hourly demand, which is calculated based on the water usage requirements of a building or structure. It is important to calculate the coincident draft accurately to ensure that the water supply system can meet the demand during a fire emergency.
Free Test
Community Answer
The coincident draft is given bya)maximum hourly demand fire demandb)m...
This is a thoerytical concept, coincident draft is the maximum of max daily demand +fire demand and max hourly demand
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer?
Question Description
The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer?.
Solutions for The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The coincident draft is given bya)maximum hourly demand fire demandb)maximum daily demand + fire demandc)maximum hourly demandd)greater of (b) and (c) aboveCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev